In General Assembly in November 2003. A particular, Gol undertook to bear the Host City Contract (HCC) was signed in financial liability for hosting of the Games, November 2003 between the by underwriting any shortfall between revenues and expenditure. 1.3 Commonwealth Youth Games took......
Governor, Delhi and Chief Minister, GNCTD to bear all costs and underwrite any shortfall between revenues and expenses November 2003 CGF General Assembly voted for allotment of XIX CWG to Delhi; Host City Contract (HCC) signed 4.1.1 Approval to IOA for bidding, grants of Rs. 518 crore and......
GLOSSARY AAI Airports Authority of India AC Bill Abstract Contingent Bill ACC Appointment Committee of Cabinet ADG Additional Director General AED Automatic External Defibrillator AFE Authorization for Expenditure AGM Annual General Meeting AIBA International Boxing Association......
The finalisation and approval of the two key planning documents for the Games - the General Organisation Plan and Games Master Schedule - were delayed by more than three years. Operational plans for different Functional Areas (FAs) as well as other planning documents of the OC were also delayed......
\_/ 1 A lanyard is a rope or cord generally worn around the neck to carry identity cards and similar objects. Performance Audit Report on XIX Commonwealth Games (CWG-2010) | 223 Chapter 15 - Workforce and Other Supporting Activities of the Organising Committee Section - C Conduct of the......
this (in March 2005), CES stadia, an evaluation committee3, on the was awarded contracts for condition survey approval of the Additional Director General and repairs for five stadia namely - MDC (TD) - CPWD, was constituted. The tenders National Stadium, Dr. S.P.M Swimming for the main......
Further, 21 of these ambulances were Advanced Life Support (ALS) ambulances, which require the services of trained doctors and are generally attached to hospitals. Only 9 ambulances were Basic Life Support (BLS) ambulances, which primarily address the need of Delhi and its citizens for......
On the basis of aspect viz. strengthening the Akshardham an assurance of the Attorney General that bund. Regarding the other measures, DDA an existing Committee appointed by the PM stated that they had written to GNCTD and consisting of Lt. Governor of Delhi as Northern Railway but could not......
Overall planning for the Games, including the General Organisation Plan, the Games Master Schedule, and the operational plans for different Functional Areas, was also substantially delayed. So was the detailed planning for state-of- the art city infrastructure in time for CWG-2010. (Chapter 5)......
the contractors in most cases. We found that generally completion of It is a matter of grave concern that despite works was delayed due to numerous lapses, the lapse of several months since the slippages, inadequacy of manpower, conclusion of the Games, final payments incompetency of......
27.7 Purchase of Electronic, Additional items were ordered from the Sports and other same contractor without tendering in 4 Equipment cases; 27.7.1 General Hire charges for facilities were paid for periods for which the facilities were not We examined 63 major contracts for Rs. available in......
In addition Rs.10 crore was Live and direct consultations with the provided for incidental/ contingency Solicitor General without routing through expenses which SIS Live stated to be pre-MIB. The Solicitor General vetted the operative expenses and unspecified contract and settled the changes,......
within the normal audit OC, and audit of its financial statements jurisdiction of the Comptroller and Auditor upto 2007-08 was carried out as such. General of India (CAG). The scope, extent Over the period of three financial years and frequency of audits of these agencies is decided through risk......
of Activities of OC OC's activities can be divided into the following broad categories, corresponding to the 34 Functional Areas (FAs) listed in the General Organisation Plan (GOP) prepared by the OC in August 2007. r 1 Section - C Sport: 5 Conduct of the I Games-Organising L 2 Committee J7 1 f1......
the OC had indicated that the sponsorship drive had slowed due to However, our concerns were not global slowdown and general elections, adequately addressed. Performance Audit Report on XIX Commonwealth Games (CWG-2010) | 129 Chapter 8 - Revenue Generation by OC In July 2009, OC sought......
4 6 It is not clear when PWD, GNCTD commenced using CPWD's manuals, contract clauses and other terms and conditions/ circulars are generally adopted by PWD,GNCTD. these higher CPOH rates. 5 Indicated in the data book itself 7 Without any additional margin for contractor's profit 4381......
Preface During the meeting of the Commonwealth Games Federation (CGF) General Assembly in November 2003, Delhi won the bid to host the XIX Commonwealth Games 2010. Flaving won the bid, the host city contract was signed......
In General Assembly in November 2003. A particular, Gol undertook to bear the Host City Contract (HCC) was signed in financial liability for hosting of the Games, November 2003 between the by underwriting any shortfall between revenues and expenditure. 1.3 Commonwealth Youth Games took......
Games (CWG-2010) Chapter 9 - Games Planning Consultancy and Overlays Industrial goods: Section - C Conduct of the Games-Organising Committee Other general/household items: Item 1 Minimum rate (per unit in Rs.) 1 1 Maximum rate (per unit in Rs.) 1 Air Freshener 266 1,456 Automatic shower......
OC 1 | I UJ 1- Q. Ceremonies < I 10 U The main ceremonial events of CWG-2010 were the Queen's Baton Relay (containing a O) 03 C U -= !E 03 message of Queen Elizabeth - II) which was to be carried through the Commonwealth w--- C 03 o CO c S>.t2 o...
cc LU 1- Q. 91 Streetscaping and Beautification < L \ of Roads around CWG Venues U L_4 Streetscape generally refers to urban roadway design and conditions as they impact street users and nearby residents. Streetscaping programmes are an important......
DC. LU 1- Q. 9? Upgradation of Street Lighting < LL of Roads in Delhi U The project for modernisation of Delhi Street Lighting System was conceived by GNCTD in June 2006, with plans to implement it across Delhi within 2 years. Detailed lighting...
CHAPTER 25 Renovation and Restoration of Connaught Place Although the project for renovation and restoration of Connaught Place was envisaged in April 2004, it was plagued by undue delays. The original estimated cost ofRs. 76 crore (as of May2005)...
CHAPTER Other Infrastructure Development Activities TETRA is a professional mobile communication service essentially meant for emergency services and government agencies. In September 2008, GNCTD decided to introduce a TETRA network in time for...
Audit Place : New Delhi Economic and Service Ministries Countersigned Dated : 20 June, 2011 (VINOD RAI) k Place : New Delhi Comptroller and Auditor General of India Section -1 Conclusion 564 | Performance Audit Report on XIX Commonwealth Games (CWG-2010)......