We further noticed that compensation amounting to ` 61.90 lakh was paid from the budget major head “2235 Social Safety and Welfare” during the year 2009 -10 to 2012 -13 to the passengers or heirs of such passengers against 1039 cases of accident from UPSRTC buses. The non............
Based on the audited accounts of the Government of Rajasthan for the year ended March 2013, this report provides an analytical review of the finances of the State Government. The financial performance of the State has been assessed based on the...
38 Minor Irrigation and Soil Conservation 99.89 21.86 21.9 9. 43 Minerals 185.53 82.11 44.3 10. 49 Compensation and Assignments to Local Bodies and Panchayati Raj Institutions 338.30 73.27 21.7 11. 50 Rural Employment 274.03 60.69 22.1 Capital-Voted 12. 19 Public Works 512.57 135.71 26.5............
stipulated payment of wages on weekly basis and not later than a fortnight from the date on which work was done (Section 3(3)), failing which compensation as per the provisions of the Payment of Wages Act 1936 (MGNREGA, Schedule II, Section 30) would be paid by the State Government. Audit............
The EPD, however, failed to adequately address the issues relating to land acquisition, Right of Ways (ROW), settlement of compensation to land owners, etc. at the planning and approval stage of the proj ect. As a result, the proj ect work, originally scheduled for completion by July 2010, was............
to 8.79 crore during 2009- 10.This was due to reduction in receipts under the head 'Receipt from FCA Act 1980' on account of elimination of crop compensation upon formation of State CAMPA in August 2009. The Department stated (October 2012) that it was difficult to estimate closely, as the............
the year 2011-12 are given in the table below: Table - 5.1.1 C in crore) Name of the Departments* Total Budget Expenditure Allocation Development Planning, Economic Reforms and North Eastern 90.05 28.61 Council Affairs Election 2.62 2.59 Excise 5.47 5.32 Finance, Revenue and Expenditure............
to financial rules/regulations and instructions led to wasteful expenditure on roads lying incomplete due to land disputes, non- levy of compensation on contractors for delayed works and acceptance of sub-st andard works by Executive Engineers. There were deviations in number of wo............
The project estimate 2002 had a provision of ` 98.75 lakh for R&R activities including ` 82.41 lakh for land compensation. The Department initiated (November 2003) the proposal and obtained (April 2008) clearance from Ministry of Tribal Affairs, GoI, with the stipulation that R&R plan would be............
A performance audit of the implementation of NRHM revealed that though baseline surveys were completed, Perspective Plans for the Mission, Annual Plans for districts, blocks and villages were not prepared regularly. Rupees 62 crore, meant for activities such as hiring private anaesthetists and............
for the year ended 31 March 2009 Appendix 1.13 (Reference : Paragraph- 1.1.8.7 ; Page 19) Revenue loss due to underutilisation of co-generation plant in MRK Co-operative Sugar Mill Target units per Units exported Short fall per No of Total units lost Revenue loss at Year day per day day............
However, the State Government had neither formulated a state policy on Education nor spelt out any vision statement. While the Perspective Plan was notfinalised, Annual Plans were prepared merely for the purpose of availing budgetary grants. The Gross enrolment ratio declinedfrom 118 in 2007............
750 50 37,500 150 75,000 Chamling Grand Total 82,15,610 Appendix -1.2.2 Statement showing the excess payment due to erroneous assessment of land compensation {Referred to in Paragraph 1.2.8.2, Page 42) Market Valuation Maket Total valuation Excess Name of acquiring Area (in rate at rate i/c............
State however, lacked in policy pronouncements and implementation as the Education Policy was not formulated, vision not spelt out, Perspective Plan not finalised, Annual Plans perfunctorily prepared for availing budgetary grants, etc. While considerable funds were blocked in incomplete school............
This Report on the Finances of the Government of Odisha is being brought out with a view to assess objectively the financial performance of the State during 2013-14 and to provide the State Government and State Legislature with timely inputs based...
Value rate is from zero to one, closer to zero inequality is less and closer to one inequality is higher Press note July 2013 Planning Commission BPL 2011-12 by Tendulkar methodology 2 SRS Bulletin, September 2013 3 Economic Survey Indicators for 2010-11 as shown in Economic Survey of 2012-13 4............
3. Lower Suktel Irrigation Project (LSIP) 1999 -00 217.13 2003 -04 Displaced families in submerged area agitated due to non payment of compensation to them and hence the project works could not be started by cont ractors and contracts were closed and awarded to Orissa Construction Corporation............
3.1. 5.2 Uncollected energy compensation charges As per provisions of the allocation order and agreement, industrial units had to pay water rate and also compensate for loss of power generation due to drawal of water from the reservoir. EEs had not raised any demands for these losses. However,............