Report No.4 of 2022 - Performance Audit of Implementation of Housing Schemes for Urban Poor in Karnataka, Government of Karnataka.
As of March 2021, under AHP and BLC verticals, projects were taken up only for 5,17,531 beneficiaries out of the 13,71,592 prospective ben eficiaries (38 per cent ) identified through demand survey. As against the approved 5,1 7,531 DUs, only 88,395 DUs (17 per cent) were completed as of...
Sector:
Social Infrastructure
AHP projects during 2015 -21, only 21, 837 (seven per cent ) DUs were completed and 2,29,774 DUs (75 per cent ) were yet to be started as of March 2021 . The reasons for the poor progress are brought out below: 3.2 Short age of Financial Resources As of March 2021, CSMC approved 3.05 lakh DUs...
Report No. 4 of the year 2022 6 lakh was wrongly credited to the account of a private person . The amou nt was yet to be recovered (September 2021). On scrutiny of records maintained at test checked 36 ULBs, Audit further observed the following : The ULBs did not have the details of...
ಇನೂು ವಸೂ ಮಾಡಬೆೋಕಾದೆ (ೆೆಿಂಬ 2021). ಪೋಾ -ಖೆ ನಡೆದ 36 ಯುಎಲಗಳು...
ಏಳು) ವಸ? ಘಟಕಗಳು ಪೂಣDೊಂ?`ೆ ಮತುತ್ 2,29,774 ವಸ? ಘಟಕಗಳು (aೇಕNಾ 75) Zಾ? 2021ರ?ಲ್ದದ್ಂQೆ ಇನೂನ್ Vಾರ್ರಂಭ`ಾಗXೇ?Sೆ. ಕಳVೆ ಪರ್ಗ?Dಾ? Bಾರಣಗಳನುನ್...
The number of BLC projects and DUs approved as of March 2021 was as follows: Table 4.1: Details of BLC projects approved as of 31 March 2021 BLC vertical No. of approved projects No. of approv ed DUs BLC ( State converged projects) 1380 143960 BLC (Non -converged projects) 792 68960 Total 2172...
ಮಾಿ 2021 ರಿದದಂತ ಅನಮ ಸಲಾದ ಎಲ ಯ ನ ಗಳು ಮನಿ ವಸ ಘಟಕಗಳ ಸಂ ಯಯನ ಈ ಕ...
The State Government while accepting the a udit observation stated (September 2021) that ULBs were instructed to recover subsidy amount from the above beneficiaries. Further the real time integration of CLSS beneficiary data with PMAY MIS was introduced (November 2019) which prevented...
18 out of 153 AHP projects approved before 27 th Meetings were yet (March 2021) to be started. Submission of proposal to CSMC for conversion of AHP to BLC projects are not forthcoming from the records made available to audit. 37 02 Grounding of earlier approved houses under AHP is not...
ಅಪಠರಯವನುು ಒಪೊಳುಳಠು (ಸೆಪೆುಬರ 2021) ಮೋನ ಫಲಠನುಭಗದ ಸಹಠಯಧನ ಮತುವನುು...
ಯೋಜನ ಳಲೆ 18 ಯೋಜನ ಳಳ ಇನೊನ ಪಳಾರಂಭವಳಬ ೋಕದ (ಮಳಚಗ 2021). ಎಹ ಚ ಯನುನ ಎಲ ಯೋಜನ ಗ...
reforms prescribed to ease the administrative and regulatory bottleneck in facilitating growth of affordable housing sector were yet (September 2021) to be fully complied by the State Governm ent. In AHP projects, t here was shortfall in aggregating financial resources as GoI withheld an...
As of March 2021, under AHP and BLC verticals, projects were taken up only for 5,17,531 beneficiaries out of the 13,71,592 prospective beneficiaries (38 per cent) identified through demand survey. As against the approved 5,17,531 DUs, only 88,395 DUs (17 per cent) were completed as of March...
1 Chapter I Introduction The Pradhan Mantri Awas Yojana – Housing for All (Urban) [PMAY (U)] launched during June 2015 envisaged provision of houses for all urban poor over a period of seven years. The Government of Karnataka (GoK) notified (May...
ಅನಸಸಬೆೇಕಾದೆ (ಸೆಪೆಿಬ 2021). ಎಹೆಚ ಯೇಜನೆಗಳಲ , ಗತ...
ಾಚಾ 2021ರಲದದತೆ ಎಹೆಚ ಮತುು ಎಲ ಘಟಕಗಳಯಲ , ಬೆೇೆ...