Page 47 of 168, showing 10 records out of 1,673 total
364.44 161.11 30.66 12 23-Industries Department 445.65 292.64 153.01 34.33 13 49-Water Resources Department 398.65 265.88 132.77 33.30 14 19-Forest, Environment and Climate Change Department 624.34 496.04 128.30 20.55 15 26-Labour, Employment and Skill Development Department 281.43 170.66 110.77......
2,204.44 Energy 1,200 554.63 1,754.63 321.48 Industry and Minerals 52.61 264.28 316.89 347.97 Transport 261.9 183.69 445.59 0 Science, Technology and Environment 0 0 0 864.76 General Economic Services 89.62 1,125.29 1,214.91 0 Grants-in-aid and Contributions 0 0 0 36,552.83 Total 22,895.38......
6. Non-levy of penalty of ` 213.32 crore for extraction in excess of quantity permitted in the environmental clearance certificat e/ permission from Pollution Control Board. 7. Non-prescription of a comprehensive checklist for f inalisation of assessment by the Commercial Taxes......
Revenue Sector 58 action taken in cases of illegal/ unauthorised extr action of minerals was effective; and, there is a system for ensuring that environmental c oncerns are being addressed properly and preventive measures are useful and effective. 6.2.4 Audit criteria The audit criteria for......
(Paragraph 6.2.13.2) Absence of system to restrict extraction of mineral to the quantity p ermitted in environmental clearance led to non-levy of penal ty equal to price of mineral amounting to 212.57 crore for excess extraction of 29.97 lakh MT of coal over the quantity permitted in......
Arvind Kumar Chaudhary Mr. Devendra Kumar Shukla Mr. Sheo Shankar Chaudhary Development Commissioner, GoB Pr. Secretary, Deptt. of Forest & Environment, GoB Principal Secretary, Finance Department, GoB Secretary, Rural Development Department, GoB Principal Chief Conservator of Forest,......
ensure all Government schools and anganwadis have access to safe drinking water; f. provide enabling support and environment for Panchayati Raj Institutions and local communities to manage their own drinking wate r sources and systems in their villages; and g. provide access to information......
They create the environment in which IT applications and relate d controls work. Main general controls, inter-alia, include organizationa l and management controls, logical access controls, program change controls, e tc. In Karnataka, audit noticed that the vital information i.e. user id and......
CHAPTER IV 4.1 Introduction Corporate Social Responsibility (CSR) is a Company’ s commitment to operate in an economically, socially and environmentally sustaina ble manner, while recognising the interests of its stakeholders including consumers, employees, investors, communities. It......
The target for ‘utilisation of fly ash’ was fixed at 70 per cent, though Ministry of Environment and Forest had prescribed 100 percent utilisation. NLC stated (September 2017) that the targets might not always be comparable with achievement in previous years. Parameter on fly ash......
cent) primarily due to effect of change in functional cur rency 79 from Indian rupee to United States Dollars (USD) considering the primary econom ic environment in which it operated. The Shipping Corporation of India recorded, the hig hest increase in profits of `375.99 crore (99.66 per cent)......
With a view to grant ing managerial and commercial autonomy to successful profit making Public Sector Enterprises (PSEs) operating in a competitive environment, the Department of Public E nterprises (DPE) enhanced the delegated powers of the Board of Directors of Navra tna PSEs in August 2005 to......
The reasons for delay attributed to AAI were non-av ailability of site, delay in obtaining environmental clearance, approval from Director Gen eral of Civil Aviation (DGCA) 11 and Notice to Airmen (NOTAM) 12, delay in approval of drawings and change in the scope of work after award of contracts.......
After approval for the mining plan (July 2 008), the Management could apply for Environment clearance and Phase-II Forest clearance . Following the clearances, various facilities would need to be created including const ruction of approach road, installation of primary and secondary crushing......
1 July 2010 to finance and promote clean environment initiatives 5 Stowing Excise Duty is levied by Government of In dia on Coal for rehabilitation, stowing and infrastructure development of abandoned mines Report No. 11 of 2018 39 Audit has worked out the loss on a conservative basis,......
on real estate development along the e xpressway had been imposed (October 2013) by the National Green Tribunal (NGT) due to raising of objections by environmental activists on the construction acti vities around Okhla Bird Sanctuary (within 10 km radius).The restrictions co ntinued at the time of......
for each location, non-submission of requisite fee, lack of proof of capital investment, land allotment letter, commitment for compliance with environmental clearance and the details of the sour ce of raw water to assist in securing clearance from Central Ground Water Authority. Some of the......
For transforming villages in the State of Maharashtra into Environmentally Sustainable Village or an Eco-Village, Government of Maharashtra (GoM) in Rural Development and Water Conservation Department (Department) launched a Scheme namely Paryavaran Santulit Samruddha Gram Yojana (August 2010).......
The Government of Maharashtra (GoM), Environment Department had initiated (2006-07) State Lake Conservation Plan (a State Scheme) with a view to conserve and beautify various lakes across the State. The total project cost was to be shared in the prescribed ratio 69 between GoM and the......
1.11.7 Implementation of Eco -friendly Villages for Sustainable Development For transforming villages in the State of Maharashtra into Environmentally Sustainable Village or an Eco- Village 11, GoM, Rural Development and Water Conservation Department (Department) launched a Scheme namely......
14 33 Performance of Basin Bridge Power Station 2.1. 18 37 Fuel Management 2.1. 20 38 Issues concerning Environment 2.1.25 40 Acknowledgement 44 Conclusion 44 Recommendations 45 Information Technology Audit of Drug Distribution Management System in Tamil Nadu Medical Services Corporation 2.2......
Issues concerning environment The emission levels of Nitrogen Oxides in GTPS were within the norms in all the five years covered by audit, but the levels of effluent were more than the permissible limit in TGTPS, VGT PS-I and VGTPS- II. In TGTPS, the accumulation of the chemical sludge was......
83 crore of minimum guaranteed off -take ch arges to GAIL for short drawal of gas on account of forced outages. Issues concerning environment The emission levels of Nitrogen Oxides in GTPS were within the norms in all the five years covered by audit, but the levels of effluent were more than......
LGB Load Gear Box LOI Letter of Intent MIS Management Information System MLD Million Litre per Day MMT Million Metric Tonne MoEFCC Ministry of Environment, Forest and Climate Change MOU Memorandum of Understanding MT Metric Tonne MU Million Units MW Mega Watt NH National Highway NIT Notice......
due to defective DPR and delay in commencement of commercial operation of units in absence of timely obtaining of requisite statutory permissions and Environmental Clearance (EC)/non-compliance with environmental conditions. Cost analysis As against the estimated cost of 25,048 crore for five......
Further CIDCO while obtaining (2010) th e environmental clearance for Navi Mumbai site stated that the Navi Mumbai site was selected considering availability of land, least expenditure for site development, aeronautical considerations and least displacement of popula tion. Considering the......
3 Chandrapur (40-49) Delay in COD due to non-renewal of Environment Clearance . Delay in finalisation of BoP contract . Delayed supplies, inadequate/inexperienced erection supe rvisory staff of BTG contractor. Delay in supply of equipment/erection by BoP contractor a nd poor......