Index //$chileFileTitle ?>
(PDF 1.12 MB)
In the above backdrop, performance audit was taken up to assess the effectiveness of planning and implementation of transmission projects by PGCIL during XI Plan (2007- 2012) along with status of augmentation of transmission network up to March 2013. Besides, an attempt has been made to......
In the above backdrop, performance audit was taken up to assess the effectiveness of planning and implementation of transmission projects by PGCIL during XI Plan (2007- 2012) along with status of augmentation of transmission network up to March 2013. Besides, an attempt has been made to......
Accordingly, performance audit was taken up to assess the effectiveness of planning and implementation of transmission projects executed by PGCIL during XI Plan (2007-2012). Besides, an attempt has been made to assess shortcomings, if any, in Grid Management by Power System Operation......
CHAPTER - 2 Audit Framework 2.1 Scope of Audit The performance audit covers all activities from conceptualisation to implementation of selected major transmission projects executed by PGCIL between......
1.4 Physical performance of PGCIL The physical performance of PGCIL during the period of last six years ended 31 March 2013 are given in Table 1.1. Table 1.1 Physical performance of PGCIL Particulars/Years 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 Length of transmission lines (in 67,000......
Towards this aim, XI Plan stipulated target of inter-regional transfer capacity of 17000 MW. 4.1 Performance vis-a-vis targets Against the XI Plan target of 17000 MW, PGCIL achieved 13900 MW of inter-regional capacity and there was a shortfall of 3100 MW. PGCIL prepared an Investment Plan of......
CERC timelines were actually meant for incentivizing exceptional performance/early completion because these timelines did not consider the time required for tendering (5-6 months) and margins for right of way, forest clearance, law and order problems, etc. MOP had also constituted a Task......
Highest number (59) of GD-3 to GD-5 categories of GDs occurred in NER, out of which 19 were of GD-5 category. Examination in audit revealed that the classification format of grid disturbances had a further scope for improvement as detailed below: 67 Category GD-1 - When less than 10 per cent......
CEA when they emphasised (May 2012) that quantifying growth of transmission capacity in terms of inter regional capacity was an inadequate index of performance. POSOCO added that it was the transfer capability across regions that was important. 3.1.3 Development of inter-regional corridors The......
Report No. 18 of 2014 Annexure- 2.1 (As referred to in Para 2.5) (A) List of projects selected for Performance Audit SI. Project Name Date of Investment Approved cost Scheduled date of No. Approval R in crore) completion Generation linked projects......
8.3.3 Quarterly Performance Review at MOP level In addition to project monitoring system at PGCIL’s level as discussed above, MOP also monitored the performance of PGCIL projects every quarter. However, status of quarterly performance review meetings held during 2007-12 revealed that such......
Out of 20 projects selected for Audit, only one was completed within scheduled time and delay was above 20 months in nine projects. Time taken in acquisition of land, handing over site and providing approved drawings to contractors, release of advance to contractors and forest clearance had......
IPPs Independent Power Producers 42. ISGS Inter State Generating Station 43. IT Information Technology K 44. kV Kilo Volt 45. KPI Key Performance Indicators 46. kWh Kilo Watt Hour L 47. LD Liquidated Damages 48. LDC Load Despatch Centre 49. LILO Loop In Loop Out 50. LTA Long Term Access M......
43 Reliability Reliability refers to the degree of performance of the elements of the bulk electric system that results in adequate and secure delivery of electricity to the consumers. Electric system reliability can be assessed through two indicators viz., adequacy and security. 44 Reliability......
in line with the National Electricity Plan, capacity building of State Utilities and DISCOMs, ATC/TTC declaration, communication planning, protection audit carried out for State Utilities, inputs for competitive bidding, coordination & support to State Transmission Utilities (STUs) viz., providing......