Overview

The Performance Audit of Saryu Nahar Pariyojana (SNP) was carried out focusing on the execution of works during April 2017 to March 2022. It aims at assessing the efficiency and economy in the implementation of the project, identifying the lapses, if any, in obtaining the benefits envisaged from the project, and suggest to the State Government for corrections and improvements.

The instances mentioned in this Report are those which came to notice in the course of test audit for the period 2017-18 to 2021-22 as well as those which came to notice in earlier years but could not be reported in the previous Audit Reports; matters subsequent to the year 2021-22 have also been included, wherever necessary.