OVERVIEW
I. Introduction
1. Important audit findings noticed as a result of test check
of transactions entered into by the Central Government Companies / Corporations
conducted by the officers of the C&AG of India under Section 619(3)(b) of the
Companies Act, 1956 or the statute governing the particular Corporations are
included in this Report.
2. This Report includes 146 paragraphs in respect of 60 PSUs.
The draft paragraphs were forwarded to the Secretaries of the concerned
Ministries/Departments under whose administrative control the PSUs are working
to give them an opportunity to furnish their replies/comments in each case
within a period of 6 weeks. Replies to 79 paragraphs were not received even as
this report was being finalised. Earlier, the draft paragraphs were sent to
Management of PSUs concerned - in respect of 4 paragraphs, they failed to
respond despite being reminded repeatedly.
3. 146 paragraphs included in this report relate to the PSUs
under the administrative control of the following Ministries/Departments of the
Government of India:
Ministry/Department
(Total number of PSUs/
PSUs
involved here) |
No. of
Paragraphs |
Financial Implication
under the Paragraphs
(Rs. in crore) |
Number of Paragraphs in
respect of which Ministry
reply
was awaited |
1. Agriculture (3/1) |
1 |
0.46 |
- |
2. Atomic Energy (4/1) |
1 |
8.02 |
- |
3. Chemicals and Petrochemicals (17/1) |
1 |
0.73 |
- |
4. Civil Aviation (7/2) |
10 |
31.42 |
9 |
5. Coal (10/5) |
13 |
375.22 |
6 |
6. Commerce (10/4) |
9 |
27.69 |
2 |
7. Consumer Affairs, Food and Public Distribution (2/1) |
5 |
42.46 |
4 |
8. Defence (9/4) |
4 |
18.96 |
1 |
9. Disinvestment and Development of North Eastern Region (1/1) |
1 |
0.69 |
1 |
10. Fertilizers (8/3) |
4 |
50.64 |
1 |
11. Finance (8/3) |
8 |
23.20 |
5 |
12. Health and Family Welfare (3/1) |
1 |
0.35 |
1 |
13. Heavy Industries and Public Enterprises (52/7) |
21 |
77.98 |
17 |
14. Information Technology (6/2) |
2 |
5.30 |
2 |
15. Mines (4/1) |
2 |
14.20 |
- |
16.Non Conventional Energy Sources (1/1) |
1 |
7.90 |
- |
17. Petroleum and Natural Gas (20/7) |
24 |
284.42 |
13 |
18. Power (11/4) |
8 |
74.69 |
6 |
19. Railways (9/1) |
1 |
1.68 |
1 |
20. Road Transport and Highways (7/1) |
5 |
19.16 |
3 |
21. Shipping (8/1) |
1 |
1.55 |
1 |
22. Small Scale Industries and Agro and Rural Development
(2/1) |
1 |
2.35 |
- |
23. Steel (17/6) |
20 |
336.37 |
6 |
24. Tourism (10/1) |
2 |
0.73 |
- |
Total |
146 |
1406.17 |
79 |
The audit observations included in this report highlight
deficiencies in the management of PSUs which resulted in serious financial
implications. The irregularities pointed out are broadly of the following
nature:
- Unproductive expenditure/imprudent investment and loss of
interest, financing charges amounting to Rs.712.72 crore in 39 cases
due to bad investments, pay and allowances of idle labour, injudicious import
of components etc.
- Excess/irregular payment of Rs.289.95 crore in 12
cases was made to staff of the PSUs on account of ex gratia, bonus,
salaries, wages, extending benefits in excess of norms etc.
- Avoidable expenditure of Rs.145.63 crore in 32
cases due to use of unproven technology, delay in installation of
equipment, failure to ensure correct specification of material,
import/procurement of spares at higher rates, detention of vessel beyond lay
time, power factor surcharge, poor cash management, payment of demurrage,
customs duty, excise duty etc.
- Loss of Rs.103.12 crore occurred in 24 cases
on account of undue favour to parties, defective agreement/contract terms,
unrealistic feasibility study, wrong estimates, failure to obtain bank
guarantee, delay in award of work, failure to make counter offer, failure to
take financial safeguards, forfeiture of earnest money deposit etc.
- Loss of revenue/sale proceeds of Rs.68.82 crore in
18 cases due to delay in realisation/non-realisation of debts, purchase
without working out parity calculations, unnecessary borrowings, manufacture
of machines without order, unwarranted restriction on production, loss of
generation of power premature deal to sell an aircraft non recovery of lease
rentals etc.
- Avoidable loss of Rs.56.66 crore in 11 cases
due to delay in finalisation of tenders, failure to invoke risk clause, non
compliance of terms of the contract, non-adherence to delivery schedule,
finalisation of contract documents without clients approval etc.
- Loss of Rs.29.27 crore in 10 cases due to
adoption of incorrect tariff, excess settlement of claims, non-realisation of
royalty etc.
II. Highlights
Gist of some of the important paragraphs included in the
Report is as follows:
- Indian Rare Earths Limited
incurred infructuous
expenditure of Rs.8.02 crore contrary to the technical recommendations
during 1997-98 to 1999-2000 on major repairs of a sick plant.
(Para 2.1.1)
- Unnecessary borrowings by the Airports Authority of
India (AAI) resulted in interest loss of Rs.10.35 crore during the
period April 1995 to March 2001.
(Para 4.1.1)
- By allotting space at lower rate in October 1998 and
allowing the same licencee to occupy adjacent land without claiming any
licence fee, AAI had to forgo revenue of Rs.6.07 crore upto
March 2002.
(Para 4.1.2)
- Under billing of electricity charges by the AAI
resulted in loss of Rs.3.80 crore during 1997-98 to 1999-2000.
(Para 4.1.3)
- By allotting space at a lower rate during February 1999 and
allowing the same licencee to illegally occupy adjacent land, that too without
payment of any licence fee, AAI had to forego revenue of Rs.2.17
crore upto March 2001.
(Para 4.1.4)
- Indian Airlines Limited (IAL)
incurred a loss of
Rs.4.83 crore during the year 2000 due to its premature deal for
delivering an aircraft to the buyer.
(Para 4.2.1)
failed to provide satisfactory ground handling
services to Oman Air resulting in loss of revenue of Rs.1.50 crore from
August 2000 to September 2001.
(Para 4.2.2)
- Bharat Coking Coal Limited
(BCCL) failed to
maintain the guaranteed ash content in the washed coal as per MOU with SAIL
and suffered a loss of Rs.17.28 crore by way of despatch of coal above
the guaranteed ash content during 1998-99 to 2001-2002.
(Para 5.1.1)
constructed 852 quarters in October 1996 at
a cost of Rs.13.87 crore for shifting/rehabilitating workers from one
area earmarked for mining but the quarters remained un-occupied till date
(August 2002).
(Para 5.1.2)
- Coal received from the Moonidih mines of BCCL was
found to be below the declared grade based on analysis at washery end. As the
declared grade was neither revised nor the grade slippage arrested resulting
in avoidable payment of royalty of Rs.5.30 crore during 1997-98 to
2001-2002.
(Para 5.1.3)
commenced a project for extraction of cooking coal
from an already developed area by underground mines without obtaining the
statutory permission from the Director General of Mines Safety. As the
permission was not granted the expenditure of Rs.3.87 crore incurred on
the project (January 1997 till its suspension in June 1999) towards
clearance of overburden became infructuous.
(Para 5.1.4)
- For rehabilitation of families from critically endangered
areas, as well as to shift workers from coal bearing area, BCCL hired
quarters from Fertilizer Corporation of India Limited. The quarters were
repaired by BCCL but could not either be occupied or the occupation was
delayed which resulted in wasteful expenditure of Rs.1.04 crore in
payment of idle lease rent from January 1996 to March 2002.
(Para 5.1.5)
- The integrated Piparwar mining and coal beneficiation
project of Central Coalfields Limited became operational from
1997-98. However, since the railway siding scheduled for completion in
March 1993 has not yet been commissioned, the rapid loading system
completed in April 1997 could not be put to use. Consequently the
investment on these facilities amounting to Rs.92.32 crore has yielded
no benefit besides CCL absorbing recurring unrecovered portion on
transport of coal by road.
(Para 5.2.1)
- Due to delay in taking suitable action to improve power
factor at prescribed level, CCL paid surcharge of Rs.1.60 crore
from 1995 to 2001.
(Para 5.2.2)
- An uninsured Dumper truck of Eastern Coalfields Limited,
caught fire in March 2000 and was severely damaged. The Director
General of Mines Safety inquiry pointed to improper maintenance of the
equipment and lack of proper training to operating people. In February 2002
the Management incurred extra expenditure of Rs.2.39 crore on
procurement of spares for repairing of the Dumper.
(Para 5.3.1)
- Neyveli Lignite Corporation Limited
(NLC) relaid
2 km. stretch of its railway siding during March 1996 to December 1997
without synchronising it with gauge conversion work of Southern Railway. This
did not yield any benefit to NLC and resulted in an infructuous
expenditure of Rs.3.17 crore.
(Para 5.4.1)
made inaccurate estimates of its income during the
financial years 1997-98 and 2000-01 which resulted in short payment of
advance tax under Income Tax Act, 1961 and avoidable payment of interest of
Rs.2.76 crore.
(Para 5.4.2)
suffered a loss of Rs.2.58 crore during
1998-99 due to under insurance of its assets in the Process Steam Plant.
(Para 5.4.3)
- Due to non-recovery of electricity charges from its
employees in contravention of the terms and conditions of the Wage
Agreement, South Eastern Coalfields Limited suffered a loss of
Rs.219.77 crore during the period from April 1999 to March 2002.
(Para 5.5.1)
- Irregular payment of Rs.3.92 crore was made by the
India Trade Promotion Orgnisation to its employees from 1996-97 to
2001-02 under an incentive scheme without prior approval of Government.
(Para 6.1.1)
- MMTC Limited (MMTC) incurred an avoidable loss of
Rs.5.28 crore due to purchase of soya seed without working out parity
calculations/ignoring negative parity during the year 1998-99.
(Para 6.2.1)
- During the currency of a valid agreement for obtaining
supply of coal of superior quality at a lower rate, MMTC entered into
another agreement in June 2000 with the same supplier for coal supply
of lower quality at a higher rate, resulting in an extra expenditure of
Rs.2.63 crore.
(Para 6.2.2)
- The State trading Corporation of India Limited (STC)
made payment of Rs.5.49 crore during the period from 1992-93 to
1999-2000 as ex gratia to its employees in gross violation of the
Payment of Bonus Act and instructions of the Government of India.
(Para 6.4.1)
- Construction of a warehouse by STC in April 2000
at Kakinada Port despite a downward trend in trading activities resulted in an
infructuous expenditure of Rs.5.11 crore.
(Para 6.4.2)
- STC ignored the opinion of an expert agency, and
invested Rs.2.15 crore in two aquaculture projects leading to loss of
the entire investment during October 2001.
(Para 6.4.3)
- STC incorrectly applied voluntary retirement scheme
guidelines during 1 to 15 February 2001 which resulted in excess
payment of Rs.1.17 crore.
(Para 6.4.4)
- Failure to monitor the quality of coffee procured through
an associate resulted in export of sub standard coffee in July/August 2000
with consequential loss of Rs.1.21 crore to STC.
(Para 6.4.5)
- Inordinate delay in submission of bills under Mid-Day-Meal
Scheme by Food Corporation of India (FCI) led to an avoidable charges
of Rs.35.86 crore on food subsidy during the period August 1995 to
July 2001.
(Para 7.1.1)
- Excess burden of subsidy to GOI amounting to Rs.3.64
crore for the year 1999-2000 to 2000-01 due to short accountal of
storage gain in Punjab Region of FCI.
(Para 7.1.2)
incurred infructuous payment of Rs.1.77 crore
during April 1999 to December 2000 due to delay in surrendering leased
land.
(Para 7.1.3)
- Bharat Earth Movers Limited (BEML)
and its subsidiary
Vigyan Industries Limited (VIL) included inadmissible items as part of
‘emoluments’ and applied incorrect formula for the payment of ex-gratia
under voluntary retirement scheme. This resulted in an extra expenditure of
Rs.13.52 crore. (BEML Rs.13.35 crore and VIL Rs.17 lakh) from 1992-93
to 2001-02.
(Para 8.2.1)
- Irregular accountal of sales by Bharat Electronics
Limited resulted in premature payment of sales tax and income tax and
consequent loss of interest of Rs.3.66 crore during 1999-2001.
(Para 8.3.1)
- National Fertilizers Limited (NFL)
failed to follow the
system of counter offer to match the lowest price earlier resulted in extra
expenditure of Rs.2.82 crore on purchases of 981 lakh bags during
August 1999 to October 2000.
(Para 10.2.1)
- Injudicious purchase of a premise at Bhopal by NFL
without assessing its requirement resulted in blocking of Rs.93.31 lakh
and loss of interest of Rs.1.20 crore for the period from January
19991 to December 2001.
(Para 10.2.2)
- The investment of Rs.44.91 crore on setting up of
Formic Acid Plant in September 1998 by Rashtriya Chemicals and
Fertilizers Limited was rendered wasteful due to poor implementation of
project, lack of market demand and high cost of production.
(Para 10.3.1)
- The New India Assurance Company Limited suffered loss
of premium of Rs.3.61 crore due to its failure to load premium for
adverse claim ratio on policies issued to Videocon group of companies between
February 2000 and March 2002, according to the policy guidelines.
(Para 11.1.1)
- The Oriental Insurance Company Limited incurred a loss
of Rs.8.57 crore due allowing of excess group discount on Mediclaim
policy issued to LIC from April 2001 to March 2002 in violation of
guidelines for Group Mediclaim policies.
(Para 11.2.1)
- United India Insurance Company Limited
(UIIC)
failed to charge prescribed rates for Group Personal Accident Policy issued to
Andhra Bank customers between November 1996 and October 2000 and
suffered loss of revenue of Rs.4.49 crore.
(Para 11.3.1)
suffered loss of Rs.3.16 crore due to short
collection of premium in three cases during the period 1997-98 to 2001-02.
(Para 11.3.2)
could not recover premium for the period
1997-98 to 1998-99 from Madras Fertilizers Limited resulting in loss of
revenue of Rs.1.84 crore.
(Para 11.3.3)
- Without ascertaining its actual requirement before
placement of order, Cement Corporation of India Limited (CCI) procured
a DG set in August 1996 which remained unutilised resulting in
avoidable expenditure of Rs.16.71 crore.
(Para 13.1.1)
- Due to hiring transportation at very high rates without
inviting open tenders, CCI incurred an avoidable extra expenditure of
Rs.3.05 crore during August 1996 to August 1999.
(Para 13.1.2)
- Bharat Heavy Electricals Limited (BHEL) supplied locos
to Railways and was required to keep the same in working condition during the
warranty period. As BHEL failed to fulfil its warranty obligations, it
could not recover lease rentals of Rs. 6.82 crore during 1997-98 to
2001-02.
(Para 13.2.1)
- BHEL had imported material during 1999-2000 and
2000-2001 without any ‘Notice to Proceed’ or supply order resulting in
locking of Rs.6.27 crore.
(Para 13.2.2)
applied incorrect rate of sales tax on the
supplies in March 1998 and subsequently paid Rs.5.06 crore during
December 1998 to March 2000 to Tax Authorities under protest.
(Para 13.2.3)
- Due to unrealistic estimates and also delay in supply of
pressure vessels in May 1996, BHEL suffered an avoidable loss of
Rs.5.03 crore.
(Para 13.2.4)
- Due to delayed execution of the contract by 14 months to 26
months and non-compliance of other terms and conditions of the contract
BHEL incurred loss of Rs.4.07 crore in March 2001.
(Para 13.2.5)
accepted in July 1994 a contract under
deemed export benefits which were not actually available and also delayed its
supplies by 38 months in February 1999 resulting in an avoidable loss
of Rs.4.03 crore on account of payment of excise duty and liquidated
damages.
(Para 13.2.6)
- Due to non-adherence of delivery schedule with a delay of
16 months to 30 months and also non-compliance of other terms and conditions
of the contract, BHEL incurred a loss of Rs.2.88 crore on
account of payment of excise duty and price reduction by the customer.
(Para 13.2.7)
- BHEL accepted an order from a private party on firm
price basis without finalising the design and engineering details. It incurred
extra expenditure (March 1999) due to increase in quantities owing to
change in design, which was not recoverable from the party. Resultantly, it
had to bear a loss of Rs.2.78 crore on the contract.
(Para 13.2.8)
- BHEL failed to include a suitable clause in the
contract for reimbursement of excise duty on design and engineering services
and as such suffered loss of Rs.1.89 crore during 1997-98 to
1999-2000.
(Para 13.2.9)
failed to place the order for procurement of
imported material and consequently hand over the same in time to the
subcontractor for fabrication of dished ends. This resulted in unfruitful
expenditure of Rs.1.77 crore due to cancellation of the order by the
contractor during 1998-99 to 1999-2000.
(Para 13.2.10)
- BHEL had not assessed the techno-economic viability of
the Closed Die Forging Shop (CDFS) in the feasibility report in terms of the
cost effectiveness. As a result, the CDFS has not been operated since
1995-96 resulting in an infructuous expenditure of Rs.1.53 crore.
(Para 13.2.11)
- Heavy Engineering Corporation Limited (HEC) started
manufacture of equipment on the basis of letter of intent without awaiting
formal order, approval of drawings and receipt of advance from the client and
incurred expenditure of Rs.6.73 crore upto March 2000 which was
taken by the purchaser on account of its poor financial health. HEC
also could not sell this equipment to alternate customers resulting in
blockade of funds to this extent.
(Para 13.3.1)
- Due to non-adherence to the established marketing
guidelines, Hindustan Paper Corporation Limited suffered a loss of
Rs.3.69 crore due to non realisation of the sale proceeds for the period
from August 1997 to March 2000.
(Para 13.4.1)
- HMT Limited incurred loss of Rs.1.03 crore
between November 1996 and August 1999 due to failure to execute order
as per delivery schedule besides blocking of funds of Rs. 23.19 lakh as
of July 2002.
(Para 13.5.1)
- Injudicious procurement of Continuous Sand Mixer and Sand
Reclamation Plant by HMT Machine Tools Limited in October 1998
resulted in wasteful expenditure of Rs.1.23 crore.
(Para 13.6.1)
- Failure of Semi Conductor Complex Limited in taking
a decision either to utilise or dispose off the land purchased in 1989
resulted in blocking of Rs.2.10 crore for over ten years and loss of
interest of Rs.2.67 crore from February 1988 to June 2002.
(Para 14.2.1)
- National Aluminium Company Limited incurred unfruitful
expenditure of Rs.12.76 crore due to premature procurement of belts on
the recommendation of the supplier during the period from August 1995 to
September 1996.
(Para 15.1.1)
- By allowing two conflicting kind of provisions in a sale
transaction during the year 1998-99, NALCO could not recover
Rs.1.44 crore from a party.
(Para 15.1.2)
- Indian Renewable Energy Development Agency Limited
entered into loan agreement based on unrealistic projections. This resulted in
avoidable payment of commitment charges of Rs.7.90 crore till March
2002 and recurring annual expenditure of Rs.1.89 crore.
(Para 16.1.1)
- Despite withdrawal of Administered Price Mechanism by the
Government of India, w.e.f 1 April 1998, due to which the proposed LPG
bottling Plant would not remain viable the Bongaigaon Refinery and
Petrochemicals Limited (BRPL) completed its construction in October
2000 which led to idle investment of Rs.23.52 crore.
(Para 17.1.1)
- BRPL incurred unfruitful expenditure of Rs.2.37
crore due to non implementation of two new technologies purchased by them
during the year 1995-96 without reviewing their viability on
realistic basis.
(Para 17.1.2)
- Bharat Petroleum Corporation Limited (BPCL) failed to
take adequate measures to protect its underground optical fibre cable which
resulted in scrapping of the Telecommunication System in 2001-02 and
infructuous expenditure of Rs.3.89 crore.
(Para 17.2.1)
sold its products on credit to a customer without
any security or execution of agreement leading to loss of sales revenue from
November 1998 to April 1999 amounting to Rs.1.70 crore.
(Para 17.2.2)
- Failure of the Hindustan Petroleum Corporation Limited
to utilise newly-constructed black oil pipeline from Mumbai Refinery to Vashi
resulted in infructuous expenditure of Rs.42.30 crore from April
1998 to March 2001.
(Para 17.4.1)
delayed surrendering land that had been rendered
surplus after shifting the LPG plant from Shakurbasti. This resulted in
avoidable expenditure of Rs.10.93 crore on lease rent for the period
from April 1994 to October 2001.
(Para 17.4.2)
- HPCL failed to either dispose off the material or store
it properly resulted in loss of Rs.1.33 crore during August 1997 to
March 2002.
(Para 17.4.3)
- The failure of HPCL to ensure the incorporation of
correct specification of the material to be used in manufacture of Trim Cooler
resulted in avoidable extra expenditure of Rs.1.22 crore during
February 1997 to March 2001.
(Para 17.4.4)
- IBP Co. Limited constructed two floating roof tanks in
1993 at a cost of Rs.1.16 crore which remained unutilised for
last nine years (July 2002).
(Para 17.5.1)
- Investment of Rs.36.44 crore by Indian Oil
Corporation Limited (IOC) on setting up of propylene separation unit at
Panipat in August 2000, went waste due to flawed estimates/assumptions and failure to review the
project in time.
(Para 17.6.1)
constructed in September 2001 a terminal at
a cost of Rs.31.07 crore to supply fuel to Independent Power Producers
without waiting for their financial closure. This resulted in facilities
remaining idle.
(Para 17.6.2)
- The decision of the IOC to acquire residential
accommodation for officers at Kolkata without a realistic assessment of future
demand resulted in the blocking of funds of Rs.5.60 crore since
September 1995.
(Para 17.6.3)
- Improper deployment of staff at IOC Delhi LPG
Bottling Plant, and excessive payment of overtime allowance, despite having
surplus manpower resulted in unproductive recurring expenditure of Rs.2.91
crore per annum.
(Para 17.6.4)
- IOC supplied High Speed Diesel (HSD) between July
1996 and December 1998 from storage points in Kerala to customers in
Tamilnadu and made an avoidable payment of irrecoverable excise duty of
Rs.1.65 crore.
(Para 17.6.5)
- Failure of IOC to nominate vessels for upliftment of
High Speed Diesel from Kuwait when nominated vessel was held up due to a
cyclone at Kandla port resulted in extra expenditure of Rs.1.45 crore
in May 2001.
(Para 17.6.6)
- Oil and Natural Gas Corporation Limited (ONGC) after
opening the bids for gas compression services decided to re-tender the work
without advance payment clause despite the recommendations of the Executive
Director (WRBC) to honour the original NIT. The delay in re-invitation of
tenders resulted in further flaring of gas to the extent of Rs.45.08 crore
between October 1998 and May 2001.
(Para 17.7.1)
took up the two Coal Bed Methane exploratory wells
for drilling in 1995-96 in Durgapur area, the expenditure of
Rs.26.36 crore made until September 1997 was rendered infructuous
due to poor cementation.
(Para 17.7.2)
- For replacing the conventional logging with Electro-logging
equipment (a new technology) in two wild-cat exploratory wells, ONGC
mobilised the equipment in June 1998. Due to non-availability of scope
of work in identified wells, the equipment was finally used, as a fait
accompli, in various other wells before demobilisation. This resulted in
avoidable loss of Rs.26.03 crore as the data obtained was not found useful.
(Para 17.7.3)
- Due to early deployment of operation and maintenance
personnel before the sailing of drillship, ONGC incurred extra
expenditure of Rs.2.25 crore from 29 December 1997 to 9 February
1998.
(Para 17.7.4)
imported spare parts from May 1999 to June 1999
for its drillships without availing exemption from payment of custom duty
which resulted in avoidable expenditure of Rs.1.25 crore.
(Para 17.7.5)
suffered a loss of Rs.1.21 crore due to
implementation of unproven and untested technology during March 1999 to
August 2000. The project had to be eventually abandoned, as it was
operationally unviable.
(Para 17.7.6)
- Failure to award job of procurement and fitting of the
propeller blades to a registered ship repair unit by ONGC led to
avoidable payment of customs duty amounting to Rs.1.10 crore during
September 1998 to August 1999.
(Para 17.7.7)
- Delay in finalisation of tender and extension to the
existing contracts at the same rates by ONGC resulted in an extra
expenditure of Rs.1.06 crore for the period from July 1998 to April
1999.
(Para 17.7.8)
- Nathpa Jhakri Power Corporation Limited
and Himachal
Pradesh State Electricity Board as well as other agencies of the GOI failed in
detecting the mistakes in the computation of the capacity of reservoir of
Nathpa Jhakri Project, before submitting the DPR for the approval of the GOI
and later before commencing the execution of the work. As a result, the
peaking availability of power during lean season would now be 1.5 hours
against 3 hours as planned earlier. This would lead to a generation loss of
713 million units per annum.
(Para 18.1.1)
- By failing to take due care at the time of finalisation of
the Memorandum of Understanding for recovering TDS from the contractor,
National Hydroelectric Power Corporation Limited (NHPC) has not realised
funds amounting to Rs.7.41 crore for more than eight years (May
2002).
(Para 18.2.1)
- NHPC did not restrict the payment of customs duty in
proportion to the actual cost of the imported equipment. This resulted in an
extra payment of Rs.2.87 crore to the contractor during November
1999 to June 2001.
(Para 18.2.2)
- Due to its failure in monitoring the progress of the
generation project, Power Grid Corporation of India Limited (PGCIL)
constructed the transmission system, 45 months in advance of its requirement.
As a result PGCIL had to bear loss of Rs.26.44 crore on account
of the interest, operation and maintenance expenditure till March 2002.
Besides, PGCIL was also not able to earn annual revenue of Rs.36.74
crore since April 2000.
(Para 18.3.1)
- PGCIL did not take cognisance of the lower rate to
explore the possibility of reduction in rates before placing the letters of
award for Kishenpur-Moga transmission system in January 1995. As a
result, it had foregone an opportunity to save extra expenditure to the extent
of Rs 28.69 crore.
(Para 18.3.2)
- Due to delay in cancellation of the unutilised foreign
exchange loan coupled with premature withdrawal of loan, PGCIL incurred
avoidable burden of Rs.5.98 crore on account of finance charges from
March 1993 to July 2001.
(Para 18.3.3)
- Non-adjustment of advance paid to M/s. Technopromexport by
Tehri Hydro Development Corporation Limited against the liability
transferred to PGCIL resulted in blocking of Rs.2.78 crore since
August 1993.
(Para 18.4.1)
- Due to failure in ascertaining the availability of
requisite wagons at selected places, IRCON International Limited had to
incur an avoidable extra expenditure of
Rs.1.68 crore on retransportation of sleepers upto April 2002.
(Para 19.1.1)
- Delay in collection of toll in the Gurgaon-Kotputli section
of National Highway No.8 by National Highways Authority of India (NHAI)
had resulted in a loss of revenue of Rs.8.76 crore from 1 January
2002 upto 14 March 2002.
(Para 20.1.1)
- Failure of the NHAI to recover extra cost from a
contractor on re-awarding of work necessitated due to fault of the contractor
resulted in a loss of Rs.4.95 crore in March 2001.
(Para 20.1.2)
- Irregular payment of royalty by NHAI to the
contractor resulted in an excess payment amounting to Rs.4.47 crore
from July 1997 upto March 2001.
(Para 20.1.3)
- Central Inland Water Transport Corporation Limited
suffered a loss of Rs.1.55 crore in October 2001 due to sale of
its three attached vessels by EPFO by auctioning them at a reserve price fixed
at their scrap value instead of reusable.
(Para 21.1.1)
- Poor judgement in assessing business potential by The
National Small Industries Corporation Limited before setting up offices
abroad resulted in infructuous expenditure of Rs.2.35 crore upto
March 2002.
(Para 22.1.1)
- Kudremukh Iron Ore Company Limited (KIOCL) along with
two other public sector undertakings floated a joint venture company (JVC) in
June 1995 to manufacture low sulphur low phosphorus pig iron and ductile iron
spun pipes. Even though KIOCL has contributed Rs.50 crore as equity in
the JVC, shares upto the value of contribution have not been allotted by the
JVC to KIOCL to keep activities of JVC outside the scope of
parliamentary control. Despite the fact that the JVC was not doing well and
against specific directions of the Government, KIOCL continued to
support the JVC with concessional loans which amounted to Rs.227.50 crore
as on March 2002 resulting in loss of interest amounting to
Rs.24.23 crore.
(Para 23.1.1)
- MECON (I) Limited (MECON) incurred a loss of Rs.1.77
crore during the period 1993-94 to 1998-99 in a project on account
of faulty preparation of estimates and incurring expenditure even after
completion of the work.
(Para 23.2.1)
- MECON incurred expenditure of Rs.1.23 crore
during 1999-2000 on preparation of tender documents without getting the
approval of the client for change in the consortium, which was pre-qualified
for the work. The expenditure was wasted as MECON could not derive any
benefit therefrom.
(Para 23.2.2)
- Due to entering into a contract with a private party
without adequate financial safeguard against non-performance of the contract,
Metal Scrap Trade Corporation Limited sustained a loss of Rs.2.56
crore in the import and sale of furnace oil during the year 1998-99.
(Para 23.3.1)
- Due to acceptance of incorrect tariff for colony
consumption, National Mineral Development Corporation Limited incurred
an avoidable extra payment of Rs.1.73 crore for the period from July
1997 to May 2001.
(Para 23.4.1)
- Rashtriya Ispat Nigam Limited (RINL) incurred a loss of
revenue of Rs.9.17 crore on account of unwanted restriction of
production of hot metal during June 1998 to March 1999.
(Para 23.5.1)
- As against the minimum required deposit, RINL
deposited amounts in excess with APSEB, which, resulted additional interest
burden of Rs.3.93 crore during the period from 1995-96 to 2001-2002.
(Para 23.5.2)
- By waiving red clause and EMD, RINL improperly
awarded a contract in December 1999 to a foreign firm, which did not
fulfil its commitment and as such suffered a loss of Rs.3.07 crore.
(Para 23.5.3)
- Without ascertaining the extra cost involved, RINL
shifted its stock yard at Delhi from Badarpur to Nangloi which resulted in
avoidable extra expenditure of Rs.2.89 crore during the period from
January 1997 to June 2000.
(Para 23.5.4)
- Due to delay in nomination of a senior official by the
Ministry and resultant delay in commencement of price negotiation, Steel
Authority of India Limited (SAIL) had to settle for higher rates for the
delivery of home coking coal during July 2000 to June 2001, resulting
in a loss of Rs.27.68 crore.
(Para 23.6.1)
- Delay in taking decision by SAIL regarding relaxing
specification of soft coking coal resulted in avoidable loss of Rs.12.18
crore during 2001-2002.
(Para 23.6.2)
incurred expenditure of Rs.7.39 crore upto
July 1998 on a boiler which could not be completed by the contractor,
with no possibility of a solution in future.
(Para 23.6.3)
extended unsecured credit to a customer in
violation of credit policy which resulted in non realisation of Rs.3.76
crore which included interest of Rs.2 crore as on 31 March 2002.
(Para 23.6.4)
granted repeated extensions during 1999-2000
to a party inspite of being aware that the latter was incurring financial
losses in the past two years. This has resulted in loss of Rs.1.99 crore.
(Para 23.6.5)
- Due to poor cash management SAIL could not honour
Credit Note-cum-Cheque issued during 1999-2000 to Railways which
resulted in levy of surcharge amounting to Rs.1.70 crore.
(Para 23.6.6)
|