CHAPTER 5
MINISTRY OF COAL
Bharat Coking Coal Limited
5.1.1 Loss of Rs.17.28 crore due to lack of proper control and
inefficient operation of washeries
Bharat Coking Coal Limited failed to maintain the guaranteed ash
content in the washed coal as per MOU with SAIL and suffered a loss of
Rs.17.28 crore by way of despatch of coal above the guaranteed ash content
during 1998-99 to 2001-2002. The MOUs signed between Bharat Coking Coal Limited (Company)
and Steel Authority of India Limited (SAIL) during 1998-99 to 2001-2002 for
supply of washed coal envisaged the guaranteed ash percentage of 18 per cent to
19.5 per cent for individual washeries of the Company with provision for bonus
and penalty for every 0.1 per cent decrease/increase ash percentage up to 1.5
per cent above the average guaranteed ash percentage fixed for each individual
washery. It was also envisaged that supply of washed coal beyond the guaranteed
ash content limit i.e. between 19.5 per cent (18 + 1.5 per cent) to 21.0 per
cent (19.5 + 1.5 per cent) would be classified as unwashed and SAIL would pay
the value of raw coal.
In order to determine the quality of washed coal MOU was
initially signed between the Company, SAIL and Central Fuel Research Institute (CFRI)
in November 1996, extended up to 1998-99, according to which CFRI was required
to analyse the washed coal produced at the Company’s washeries and supplied to
SAIL at loading point. The result of the sampling and analysis was binding on
both the parties. Subsequently, for the years 1999-2000 to 2001-02 tripartite
agreements were signed between BCCL, SAIL and Mineral Exploration Corporation
Limited (MECL) for determination of quality of washed coal by MECL on rake to
rake basis at loading point. The analysis of MECL was binding on both the
parties.
The maintenance of quality of washed coal depended on a host
of parameters namely washability test of raw coal, adjustment of gravity of the
washing equipment based on quality of raw coal, proper maintenance and operation
of the equipment to avoid leakage, inter mixing and ingress of chemicals in the
washed coal, which required constant supervision, quality control, proper
maintenance and operation of equipment in the washeries.
However during period 1998-99 to 2001-02 the washed coal
supplied by the washeries of the Company exceeded the ceiling limit over the
guaranteed ash percentage and in process the Company had to sustain a loss of
Rs.17.28 crore on despatches of 2.11 lakh tonne of washed coal which was
classified as unwashed and valued as raw coal.
The contention of Management (April, June and October 2000)
that quality slippage was mainly due to deterioration in quality of raw coal and
technical problems of washeries is not tenable as the tolerance limits decided
by Management while entering into MOUs with SAIL presumably took into
consideration the problems of washeries. Besides, neither had any investigation
been carried out to identify reasons for slippage so that corrective actions
could be taken nor had any reasons for slippage been recorded, except in a few
cases where the Project Officers were pulled up for quality slippage.
While accepting the facts Ministry stated (June 2002) that
Management has failed to match the quality of coal mentioned in the MOU signed
with SAIL mainly due to the age of the plants and lack of modernisation and
renovation. The views of Ministry are not maintainable on the ground that
Management while entering into MOU with SAIL must have duly considered these
factors. Besides, the Chief of the Washeries had issued a letter in December
2000 stating that ‘Area General Manager has been made exclusively responsible
for maintaining quality of raw coal, arrangement of raw coal input to Washaries
and also for maintaining strict quality parameter of washed coal produced’. The
fact that the quantity of washed coal classified as raw coal had come down
during 2001-02 with existing plant and equipment goes to show that the slippage
on quality of washed coal was not on account of age of the plant but because of
the apathy and lapses on part of the Area General Manager of the washeries by
not carrying out effective and proper monitoring and quality control.
Thus, lack of proper quality control and in-efficient
operation of washeries resulted in loss of Rs.17.28 crore to the Company between
1998-99 to 2001-02.
5.1.2 Blocking of funds of Rs.13.87 crore on construction
of quarters and loss of interest of Rs.9.15 crore thereon
Bharat Coking Coal Limited constructed 852 quarters in
October 1996 at a cost of Rs.13.87 crore for shifting/rehabilitating workers
from one area earmarked for mining but the quarters remained unoccupied till
date (August 2002).
The Company constructed 852 miners quarters at Karmatand
Township in October 1996 for shifting/rehabilitating workers from Tirsa area,
which was earmarked for mining. The construction, which commenced in January
1991 and was scheduled to be completed in April 1992 at a cost of Rs.6.66 crore,
could finally be completed only in October 1996 at a cost of Rs.13.87 crore.
The quarters, however, remained unoccupied till July 2002.
The liability of the contractors to rectify defects free of cost expired in
October 1997.
Management stated (June 2001) that immediately on completion
of the work the quarters were allotted for occupation of employees. However,
local villagers obstructed the occupation claiming more employment from the
Company. Attempts were made to get them occupied but the efforts failed.
Management further stated that some headway was being made and quarters may be
occupied by 2001-2002.
The contention of Management is not tenable. Although, the
construction was completed in October 1996, the allotment of quarters had not
been done until November 1999. The agitation of local villagers had started even
before the construction commenced in January 1991. A special task force,
constituted in June 1990 to process the case for offer of employment, had
recommended extending employment to 100 persons, which were agreed to by
Management. Management made little effort after that to find a permanent
solution to the problem. A Land Committee Cell was constituted only in July
1997, which deliberated the issue for six months with no result. Thereafter till
2001-02 no tangible efforts were made by Management to sort out the problem and
get the quarters occupied.
Thus, the decision of Management to commence the project was
not based on sound and realistic assessment of its capabilities to solve the
local problem. Hence the decision to invest money on such a venture was not
prudent. The utilisation of these quarters remains uncertain. The expenditure of
Rs.13.87 crore, which did not meet the objective of shifting/rehabilitating
employees from Tirsa area, remained blocked with consequential loss of interest
of Rs.9.15 crore (@ 12 per cent on Rs.13.87 crore) from November 1996 to March
2002. Besides, the annual wear and tear of the quarters and the expenditure of
Rs.11.58 lakh paid towards security charges up to March 2002 made the position
even worse.
The matter was referred to Ministry in July 2001; their reply
was awaited (September 2002).
5.1.3 Avoidable payment of royalty of Rs.5.30 crore
Coal received from the Moonidih mines of Bharat Coking Coal Limited since
1997-98 was found to be below the declared grade based on analysis at washery
end. The declared grade was neither revised nor the grade slippage arrested
resulting in avoidable payment of royalty of Rs.5.30 crore.
Royalty on coal is paid on the basis of the grade of coal
declared at the beginning of each year by the mining companies in pursuance of
the Colliery Control Order, 1945. Accordingly, the Company, at the beginning of
each financial year, declared grade of working seams in its collieries.
Moonidih mines of the Company had been supplying coal
directly through conveyors to its Washery. The declared grades in respect of
these mines were Steel Grade II, Washery Grade II and Washery Grade IV. However,
as per analysis done at the washery from June 1997 onwards, based on the
weighted average of maximum ash percentage of each grade of coal, there were
recurring grade slippage. Although the washery head, in January 1999, advised
Management of the Moonidih mines to review and revise the grade declaration of
coal to avoid payment of royalty at a higher rate than the actual as per
analysed grade, it neither revised the grade declaration nor took any step to
stop the recurring grade slippage. This resulted in avoidable payment of Rs.5.30
crore as royalty on declared grades during the period from 1997-98 to 2001-2002.
While accepting the facts, Ministry inter alia stated
(March 2002) that possibility of separately stacking and transportation of coal
of ST II ‘Grade’ by changing/modifying the existing transport layout was being
explored.
As the grade slippage was occurring consistently since
1997-98 Management should have initiated steps either to review the grade
declaration each year or to change/modify the existing transport layout.
Management, however, did not take any steps to stop the recurring grade
slippage.
As a result of non-revision of grade of coal based on
analysed results Company made an avoidable payment of Rs.5.30 crore as royalty.
5.1.4 Infructuous expenditure of Rs.3.87 crore on a suspended
project
Bharat Coking Coal Limited commenced a project for extraction
of coking coal by open cast method without obtaining the statutory permission
from Director General of Mines Safety. As the permission was not granted the
expenditure of Rs.3.87 crore incurred on the project towards clearance of
overburden became infructuous.
Coal India Limited (CIL), based on recommendations of the
Company, approved a project in August 1991 for extraction of coking coal from
Block III under open cast mining system for Rs.45.97 crore.
The Company issued a notice in December 1996, to Director
General of Mine Safety (DGMS), besides others, to open Block-III open cast
project at Phularitand Colliery and commenced the project in January 1997. As
the extraction was of an already developed area by underground mines,
permission/exemption of DGMS was mandatory before extraction of developed coal
pillars by open cast method. Accordingly, the Company sought the
permission/exemption of DGMS under regulations 100(1) and 98(1)(3) of the Coal
Mines Regulation, 1957 in June 1997 and again in May 1998. DGMS refused to grant
permission in July 1998 and stated that the Company had commenced work on the
project before applying for permission. The work on Block III was suspended in
June 1999.
Consequently expenditure of Rs.3.87 crore incurred by the
Company on the project towards removal of overburden, from commencement of the
project in January 1997 until its suspension in June 1999, became infructuous.
The Company decided in August 2000 to keep the project in
frozen list of monitoring and in October 2000 to amortise the expenditure in
three years commencing from 1999-2000.
Management stated (April 2001) that the project was commenced
based on the project report, which indicated solid barrier between eastern and
western side of developed coal seams. But after excavation started the solid
barrier was found to be doubtful as it could expose eastern side to the fire of
western side. The project has been frozen until the fire is controlled and the
cost incurred on removal of overburden should not be treated as infructuous.
The contention of Management is not tenable, as it was
injudicious to proceed with the project without the approval of DGMS since the
extraction was of an already developed area by underground mines and involved
extraction of developed coal pillars by open cast mining method. Even after
refusal of permission in July 1998 the Company continued with the project till
it was suspended in June 1999.
Ministry in its reply (September 2002) reiterated the stand
taken by Management and stated that in normal course during formulation of a
project and commencement of extraction of coal, approval of DGMS was not
required. It further stated that Management was trying to control the fire for
which Rs.5.78 crore had been sanctioned to restart the project
The contention of Ministry is not tenable. The project
involved extraction of developed coal pillers by opencast method from an already
developed underground mine for which permission of DGMS was required. Fund
sanctioned by the Department of Coal is for control of underground fire, which
had to be stopped for reasons of safety. Whether the project could be restarted
would depend on its feasibility after the undergroung fire is controlled and
subject to approval of DGMS.
As the project stood frozen and the expenditure had been
amortised, the expenditure of Rs.3.87 crore incurred on removal of overburden
had become infructuous.
5.1.5 Wasteful expenditure of Rs.1.04 crore due to
payment of idle lease rent on vacant quarters at Sindri
For rehabilitation of families from critically endangered
areas, as well as to shift workers from coal bearing area, the Company hired
quarters from Fertilizer Corporation of India Limited. The quarters were
repaired by Management but could not either be occupied or the occupation was
delayed which resulted in wasteful expenditure of Rs.1.04 crore in payment of
idle lease rent.
With the object of shifting workers from the coal bearing
areas as well as the endangered areas, of Jharia Coalfields, the Company entered
into three separate Memorandums of Understanding (MOUs) with Fertilizer
Corporation of India Limited (FCIL) from December 1995 to November 1997 for
hiring of 1032 quarters for five years on ‘as is where is basis’ with license
fee varying from Rs.302 to Rs.632 per month and water charges from Rs.15 to
Rs.25 per month The payments of license fee and water charges were of fixed
nature depending on the type of the quarters subject to revision of lease.
Electricity charges were payable separately as per actual consumption. From the
MOUs, it was seen that the quarters were not immediately habitable and required
extensive repair. Out of 1032 quarters, the Company took over 1007 numbers of
quarters. Of these, only 683 have been occupied, 267 quarters have been repaired
but not occupied, 33 quarters are still under repair and the balance 24 are
irrepairable.
In entering into MOUs with FCIL for taking over the quarters
on “as is where is basis”, Management, in effect, committed itself to payment of
lease rent from the date of taking over of these quarters though they were not
habitable. The repair of these quarters was taken up in phased manner as per
availability of funds. It was seen that of the 683 quarters occupied by the
employees, the time taken for occupying them ranged from 1 to 34 months from the
date of completion of the repairs. Moreover, even after repair, a large number
of quarters could not be occupied. Hence the delay in occupation of the
quarters, non occupation of the quarters even after repair, delay in getting
quarters repaired and non surrendering of ir-repairable quarters resulted in
wasteful expenditure of Rs.1.04 crore by way of payment of idle rent (March
2002).
While accepting the facts, Management stated (July 2001) that
the quarters were not in a habitable condition and that repair work was taken up
in a phased manner as per availability of funds and that efforts would be made
to complete the occupancy within the current financial year. The return of 24
quarters, which were ir-repairable, was in process. It was further stated that
expenditure on repair and lease rent would not be infructuous after the quarters
were occupied.
The contention of Management is not tenable. The quarters
were taken on lease to shift the employees from endangered areas on emergency
basis as well as to shift workers from coal bearing areas. As the quarters were
not habitable the decision to take over these quarters on ‘as is where is
basis’with commitment to payment of lease rent from the date of taking was
essentially a flawed decision. Further, fund constrains also required that only
the basic essential repairs were undertaken. Eventually, Management could not
even ensure the occupancy of all the quarters, which were repaired. In summary,
the delay in occupation of the repaired quarters, non-occupation of quarters
even after repair, delay in repair of some quarters and non-surrendering of the
irreparable quarters not only defeated the purpose of lease and expenditure on
repair but also resulted in a wasteful expenditure of Rs.1.04 crore on payment
of idle rent and water charges (March 2002).
The matter was referred to Ministry in July 2001; their reply
was awaited (September 2002).
Central Coalfields Limited
5.2.1 Idle investment of Rs.92.32 crore on railway siding and rapid
loading system of Piparwar Project
The integrated Piparwar mining and coal beneficiation project
of Central Coalfields Limited became operational from 1997-98. However, since
the railway siding scheduled for completion in March 1993 has not yet been
commissioned, the rapid loading system (RLS) completed in April 1997 could not
be put to use. Consequently the investment on these facilities amounting to
Rs.92.32 crore has yielded no benefit.
The Piparwar integrated mine-cum-coal beneficiation project
of the Central Coalfields Limited (CCL) was approved by the Government of India
at an estimated cost of Rs.542.43 crore in September 1989, revised to Rs.838.27
crore in 1993, on a turn-key basis with the foreign exchange component of the
project cost covered under Australian credit. The project envisaged inter
alia a railway siding at Piparwar so that beneficiated coal could be loaded
into railway wagons by a mechanised loading system and dispatched through the
railway siding.
The construction of railway siding Phase I (14 kms) was
awarded to Indian Railway Construction Company Limited now IRCON International
Limited (IRCON) in March 1990 for Rs.13.42 crore (revised to Rs.27.09 crore in
March 1995), even before initiating any steps for acquisition of land, to
facilitate IRCON to prepare the design, engineering drawings, and get it
approved from the Railways. The time frame as initially envisaged was 3 years
for the completion of the Project i.e. it was to be completed by March 1993. The
construction of Phase II (17 kms) of railway siding was awarded to IRCON in
March 1995 at an estimated cost of Rs.41.24 crore to be completed within 3 years
i.e by March 1998. The work is still incomplete (September 2002).
The applications/requisitions for acquisition of forest land,
tenancy land and GMK (Gar Majarua Khas) land were made only between June 1990 to
January 2002 even though Ministry had in May 1988 directed the CCL to take all
necessary action on top priority basis for obtaining environmental clearance,
acquisition of land and for development of other infrastructure like
construction of railway siding. The forestland had been transferred to CCL in
February 1995. Though notifications under the Land Acquisition Act for
acquisition of most of the tenancy land had been issued between November 1992 to
February 1994 little effort was made by Management to get the physical
possession of entire land. Requisitions for some tenancy land were issued as
late as October 2000. Even the transfer of entire GMK land has not been
completed (September 2002).
As a result, even though the major components of the
integrated project such as development of open cast mines, Coal Handling Plant (CHP),
& Coal Preparation Plant (CPP), became operational in April 1997, the railway
siding work has been bogged down due to the total apathy shown by the Company in
the matter of land acquisition as brought out in the preceding paragaph.
The outcome was that washed coal of the project was being
despatched to consumers by engaging private transporters through a nearby
railhead, Bachra (8-9 kms) and in the process CCL had to absorb the unrecovered
portion of transport cost of Rs.8.14 crores for the period from 1998-99 to
2000-2001.
Management stated (May 2001) that the siding was likely to be
completed in March 2002. Ministry while accepting the fact of delay in
possession of land had inter alia stated (January 2002) that obstruction
created by the villagers would be cleared by January 2002 provided land
constraints were removed.
However till date (September 2002) physical possession of
land required for construction of the railway siding had not been obtained.
Thus, due to improper project management in awarding the work before acquisition
of land, inordinate delay in initiating the process of land acquisition, and
lack of effective follow up action with the State/District administrative
authorities for the physical possession of the land, the railway siding which
was initially scheduled for completion in March 1993/March 1998 could not be
commissioned. Consequently, the RLS which was completed in April 1997 at a cost
of Rs.4.31 crore was lying idle and the investment of Rs.92.32 crore on railway
siding had also yielded no benefit; besides CCL was absorbing unrecovered cost
of Rs.8.14 crore for 1998-99 to 2000-01 on transportation of coal through
private transporters.
5.2.2 Avoidable payment of power factor surcharge
Due to delay in taking suitable action to improve power
factor at prescribed level, the Central Coalfields Limited paid surcharge of
Rs.1.60 crore from 1995 to 2001 of which Rs.1.18 crore was avoidable.
CCL buys power from Damodar Valley Corporation (DVC) to meet
the needs of its collieries and washeries. In December 1994, DVC decided to levy
surcharge from the consumers with effect from April 1995 in the event of average
monthly power factor ( Ratio of power consumed
to power drawn through an electrical installation)
falling below 0.85. Every fall in power factor by 0.01 would attract surcharge
at one per cent of normal tariff.
The power factor recorded at Kathara Area of CCL had been
lower than 0.85 since November 1994. It was, therefore, imperative on the part
of Management to install capacitors to maintain the power factor at the
prescribed level to avoid payment of surcharge. With a view to maintain the
prescribed power factor, CCL engaged (March 1995) M/s. Andrew Yule & Company
Limited (AYCL) for design and installation of capacitors at a cost of Rs.67.53
lakh. The capacitors installed in March 1999 failed during the commissioning.
The defective capacitors had neither been replaced till date (November 2001) nor
had the work been entrusted to another party at the risk and cost of AYCL as the
agreement between CCL and AYCL did not contain any such clause. As a result, CCL
had not been able to maintain the prescribed power factor and continued to pay
power factor surcharge. During the period 1995 to 2001 CCL paid surcharge
aggregating Rs.1.60 crore due to the failure to maintain the power factor at the
prescribed level. Even assuming that a period of one year (from April 1995 to
March 1996) was needed for design and installation of capacitors, the payment of
power factor surcharge aggregating Rs.1.18 crore for the period from 1996 to
2001 was clearly avoidable.
Management stated (May 2000) that AYCL could not install the
capacitors due to some technical defects. Further, Ministry, inter alia,
stated (November 2001) that the issue was taken up (August 2001) with AYCL for
immediate completion of the job. It also stated that AYCL was selected due to
the complex nature of work and termination of contract with them for getting the
work done by some other agency, in the context of completion arising out of
repeated failure of capacitors, was not considered prudent.
Although the Company initiated action for installation and
commissioning of capacitors over five years ago, it had been unable to
commission them till date (November 2001). This led to avoidable payment of
surcharge of Rs.1.18 crore.
The matter was referred to Ministry in May 2001; their reply
was awaited (September 2002).
Eastern Coalfields Limited
5.3.1 Extra expenditure of Rs.2.39 crore on a Dumper damaged in fire
An uninsured Dumper truck of Eastern Coalfields Limited,
caught fire in March 2000 and was severely damaged. The Director General of
Mines Safety inquiry pointed to improper maintenance of the equipment and lack
of proper training to operating people. Management incurred extra expenditure of
Rs.2.39 crore on procurement of spares for repairing of the Dumper.
Eastern Coalfields Limited (Company) commissioned one Dumper
(445E Dump Truck) in December 1993. In March 2000, while working in the project,
the control panel of the Dumper caught fire and was severely damaged. The Dumper
had worked for only 15175 hours (38 per cent) as against the expected life of
40000 hours and its depreciated value was Rs.85.86 lakh as on the date of fire.
It had not been insured as per normal practice of the Company.
Management decided (February 2001) to repair the Dumper and
procure spares worth Rs.2.39 crore from the original supplier (Bharat Earth
Movers Limited). The repair work was in progress (August 2002).
The Director General of Mines Safety (DGMS) in his report
(October 2000) stated that improper maintenance of the equipment and lack of
proper training of operating people to deal with the fire resulted in huge
damage to the equipment. The DGMS in his report recommended installation of
‘Automatic Fire Protection System’ and loud alarm.
Management stated (December 2001) that Automatic Fire
Suppression System was initially provided but the same did not last because of
weak structural parts. They further stated that fire took place at a place far
from garage/parking place and it took some time to arrange for suitable fire
extinguisher, by which time fire engulfed the Dumper and it was under regular
maintenance and there was no maintenance lapse. Thus, Management’s contention
was that the entire damage was due to carelessness and negligence on the part of
the operator. Ministry inter alia stated (July 2002) that a sudden
leakage may occur inspite of optimal maintenance practice.
Management as well as Ministry’s reply is untenable in view
of the fact that independent enquiry conducted by the DGMS pointed out that
deficiencies in proper maintenance of equipment and inadequate training to
operators to deal with fire were the major reasons for the damage to the
equipment.
Had Management been more careful to provide proper
maintenance to the Dumper and arranged for proper training to operators to deal
with fire, the damage to the Dumper as well as extra expenditure of Rs.2.39
crore to repair the same could have been avoided. Management had also not
insured the Dumper against the risk of fire and other damage.
Neyveli Lignite Corporation Limited
5.4.1 Infructuous expenditure on relaying of railway siding
Unjustified relaying of metre gauge railway siding when gauge
conversion work of Southern Railway was progressing resulted in infructuous
expenditure of Rs.3.17 crore.
Neyveli Lignite Corporation Limited (Company) had a metre
gauge railway siding of 15.749 kms for rail movement of their products. The
Company shifted the loco shed to a new location due to Thermal Power Station I
Expansion Project. The Company had to dismantle a stretch of 2 kms railway track
and relaid the same in metre gauge. The rerouting started in March 1996 was
completed on 31 December 1997 at a cost of Rs.3.17 crore.
Scrutiny revealed that after rerouting, the siding had been
used for just seven months and had transported only a meagre 34385 tonne of
material. The Company had not synchronised the work with the gauge conversion
programme of Southern Railway who opened to traffic the Chennai-Trichy broad
gauge line on 1 September 1998. The metre gauge line which includes the relaid
stretch of 2 kms will necessarily have to be converted to broad gauge line for
rail transportation when Southern Railway completes gauge conversion work on the
Salem-Cuddalore line which would connect the Company’s railway siding to the
Chennai-Trichy broad gauge line. Thus, the entire expenditure on rerouting the
metre gauge line was rendered infructuous.
Management stated (July 2001) that shifting of railway siding
was necessitated by Thermal Power Station I Expansion Project and that when the
work on shifting of railway siding was started in March 1996, there was no firm
commitment on gauge conversion of the Chennai-Trichy line. They further added
that as the relaid line was with broad gauge standards, conversion of the same
to broad gauge could be done with minimum cost. Ministry (December 2001)
endorsed the views of Management.
The reply is not tenable as the necessity for dismantling a
portion of the existing line is not the issue. Also the broad gauge conversion
of Chennai-Trichy line was taken up by Southern Railway in 1992 and completed in
1998. The Southern Railway reported physical progress on conversion up to March
1996 as 29 per cent. Therefore, the Company’s decision in March 1996 to relay
the dismantled siding again in meter gauge was not correct. The line after
rerouting was used for only seven months and there was no traffic movement since
August 1998 to date (July 2002). Further on conversion to broad gauge of the
Salem-Cuddalore line by Southern Railway at a later date, the entire railway
siding including the relaid line will have to be dismantled again which would
necessarily involve additional cost, even if retrieved material is put to use.
Thus, the Company’s injudicious decision to relay the line
without synchronising the same with the gauge conversion work of Southern
Railway did not yield any benefit to the Company, and resulted only in an
infructuous expenditure of Rs.3.17 crore.
5.4.2 Avoidable payment of interest due to short payment of advance tax
Incorrect estimation of income and consequent short payment of advance tax by
Neyveli Lignite Corporation Limited resulted in avoidable payment of interest
amounting to Rs.2.76 crore under Income Tax Act.
As per Section 208 read with Section 211 of the Income Tax
Act 1961 (Act), every Company is required to pay advance tax of not less than 15
per cent /45 per cent /75 per cent on due dates in quarterly instalments (15 of
June/September/December) in such a way that the entire tax payable for the
assessment year is paid by 15 March for the respective year. As per Section 234
C of the said Act in the event of short payment, the Company is liable to pay
interest at the rate of 1.5 per cent per month on the unpaid amount of advance
tax.
The Act further stipulates that, if the advance tax paid by
the Company on its current income on or before 15 June or 15 September is not
less than 12 per cent and 36 per cent respectively of the tax due on the
returned income, then it shall not be liable to pay any interest on the amount
of shortfall on those dates.
The Company paid advance tax during the first three quarters
for the financial year 1997-98 (assessment year 1998-99) and second quarter of
financial year 2000-2001 (assessment year 2001-2002) which fell short of limits
as prescribed in the Act. As a result, the Company paid interest of Rs.1.88
crore for the year 1997-98 and Rs.1.65 crore for the year 2000-2001 under
Section 234C of the Act.
While certain items of exceptional nature such as receipt of
arrears of subsidy from FICC (Fertilizer
Industry Co-ordination Committee) (Rs.23 crore)
in the financial year 1997-98 and disallowance of part of VRS
(Voluntary Retirement Scheme)
compensation (Rs.35.38 crore) as deduction in the financial year 2000-2001 could
not be foreseen, there were certain other elements which should have been
included in the computation of taxable income. They were as below:
- The Company had estimated and accounted for additional
income (Rs.7.32 crore) on account of re-commissioning of LEP units in the
accounts for the year 1996-97. However, such income (Rs.7.18 crore) was not
estimated and spread over all the quarters but included only during
finalisation of the accounts for the year 1997-1998, pending Tamil Nadu
Electricity Board (TNEB) approval.
- Hike in revenue due to provisional increase in tariff
(Rs.8.97 crore) as per Power Supply Agreement in vogue, was not estimated
and spread over all quarters but included only in the year end.
- Generation of power was consistently exceeding the target
right from the first quarter of financial year 1997-98 but additional
revenue (Rs.56 crore) was not estimated and included in all quarters but
only in the third quarter.
Management stated (February 2002) that all the above items
were exceptional and could not be foreseen in the first three quarters.
The reply is not tenable as these items were not casual and
non-recurring. While for the first two items the Company was aware of accrual of
additional revenue, the estimate for the third item could have been made with
reasonable accuracy based on past experience and spread over all quarters.
As regard financial year 2000-2001, assessment year
2001-2002, the Company stated (February 2002) that the Power Tariff Agreement
for Thermal Station-I with TNEB was firmed up on 9 March 2001 and that income
tax reimbursement by TNEB was firmed up in the third quarter. The Company
further stated that pending finalisation of the agreement, it had reckoned only
provisional figures relating to sale of power excluding tax reimbursement of
Rs.115.96 crore. As the recognition of tax liability goes along with recognition
of income, the Company should have reckoned the revenue including the grossed up
tax reimbursement also.
Despite availability of cushion in the payment of advance tax
viz. 3 per cent in first quarter and 9 per cent in second quarter for shortfall
in payment, the Company had not determined the advance tax accurately. Failure
on this account resulted in avoidable payment of interest of Rs.2.76 crore.
Apparently Company’s tax planning machinery was not up to the mark.
The Company had filed petitions for waiver of interest under
Section 234 of the Act with Income Tax Department in respect of financial years
1997-98 and 2000-2001 and the case was yet to be decided by Income Tax
Department (September 2002).
The matter was referred to Ministry in June 2002; their reply
was awaited (September 2002).
5.4.3 Loss due to under-insurance
Consequent upon a major fire in May 1998 an expenditure of
Rs.5.98 crore was incurred towards restoration of the Process Steam Plant.
Under-insurance of the assets resulted in loss of Rs.2.58 crore. Process Steam Plant (PSP) of the Company caters to the steam
requirement of Fertilizer Plant and Briquetting and Carbonisation Plant. The PSP
was insured at 100 per cent of the original cost duly inflated by the RBI Index
except during 1997-98 and 1998-99 when insurance was made ‘based on the risk’ in
order to reduce the burden of premium payments.
A major fire broke out in PSP on 28 May 1998 causing
extensive damage to the instrument control panels, cables and control room. The
PSP was not fully covered by Fire and Explosion Policy with the sum insured
being only Rs.63.57 crore against the full value of Rs.168.77 crore. An
insurance claim was lodged (February 1999) for a sum of Rs.6.35 crore, being the
estimated expenditure for restoration activities after the fire accident. The
actual amount incurred on restoration of PSP was Rs.5.98 crore.
The Company stated (April 2002) that under-insurance in
respect of equipment at Process Steam Plant during 1998-99 was as per method
followed for thermal units in that year. They further added that against the
claim of Rs.6.35 crore an amount of Rs.1.22 crore was expected to be realised.
Against the said claim the insurance Company proposed
(February 2002) to settle Rs.1.18 crore only to NLC. Apart from certain
disallowances for Rs.1.77 crore towards improvements, salvage etc. the major
amount disallowed was on account of under-insurance, which stood at Rs.3.03
crore.
The premium payable for the period (1997-98 and 1998-99) by
the Company for the full value of assets in PSP amounted to Rs.72.23 lakh. The
Company paid Rs.27.20 lakh due to under-insurance of the PSP and saved Rs. 45.03
lakh. The saving in premium was meagre as compared to the loss suffered by the
Company due to rejection of claim on account of under-insurance. Thus, as a
result of the injudicious decision to under insure the risk, the Company had to
bear the expenditure of Rs.2.58 crore (Rs.3.03 crore minus Rs.45 lakh) resulting
in loss to that extent.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
5.4.4 Infructuous expenditure on effluent treatment plants
Effluent treatment plant constructed for treating phenolic
effluent could not achieve the prescribed standards even after 3 years of
commissioning resulting in infructuous expenditure of Rs.54.49 lakh. Tamil Nadu Pollution Control Board (TNPCB) issued (December
1995) a show cause notice to the Company for discharging the effluents without
proper treatment from the Briquetting and Carbonisation (B and C) Plant and
warned of severe action for failure to take remedial measures. The Company
promised to comply with the TNPCB standards by 31 March 1997 by upgrading the
existing effluent treatment system.
The Company issued an express press tender (October 1996) to
install systems on turnkey basis to upgrade and augment the existing
Bio-Technological Plant for treating phenolic effluent and for treating Spent
Caustic Lye. The work was awarded (March 1997) to M/s. Aqua Chemicals and
Systems (MFG) Limited, Chennai (Party) at a cost of Rs.1.61 crore, with the
stipulation that the systems should be commissioned to the satisfaction of
TNPCB’s requirements by September 1997. The said systems were commissioned in
December 1997.
It was seen that the systems did not stabilise even after
three years of commissioning and the relevant clearance certificate from TNPCB
was not obtained. The Party had no concrete proposals to achieve the standard
norms of the effluent as per the terms and conditions of the contract. Although
National Environmental Engineering Research Institute, Nagpur (NEERI) was
prepared to conduct field study, render consultancy/technical services and
requested (August 1999) to depute the Company’s officers for further discussion,
the Company did not utilise the services at the risk and cost of the Party but
continued to issue notices to the Party to complete the work by 31 January 2001.
Meanwhile, production in B and C Plant was suspended from 4 April 2001 due to
heavy financial loss. This had rendered the expenditure incurred on pollution
control systems futile.
Management admitted (February 2002) failure of Phenolic
Treatment Plant and Spent Lye Treatment system and stated that they had
recovered from the contractor an amount of Rs.1.07 crore by way of bank
guarantee, liquidated damages and non-payment of balance amount. It also stated
(February 2002) that the contract was awarded after ascertaining the Party’s
ability and track record, conforming to the notice inviting tender. But this
should be viewed against the Company’s professed lack of expertise to spell out
the detailed scope of work indicating technical specifications and to judge the
claims of various suppliers in the field to ensure that the effluents conform to
the TNPCB standards. The Company, though recognising the need to appoint an
independent consultant to study and design a suitable system, chose to give
itself very little time and was constrained to award the work on turnkey basis
to the Party in March 1997 against the deadline for completion of work by March
1997. Thus, due to delay of over one year to take action after receipt of
TNPCB’s notice, the Company was under pressure to show TNPCB that some action
had been initiated which ultimately resulted in infructuous expenditure of
Rs.54.49 lakh.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
South Eastern Coalfields Limited
5.5.1 Avoidable loss
Due to non-recovery of electricity charges from its employees
in contravention of the terms and conditions of the Wage Agreement, the Company
suffered a loss of Rs.219.77 crore.
The wage structure and terms and conditions of service
including fringe benefits of the employees in the Coal Industry are regulated by
the recommendations of the Central Wage Board for Coal Mining industry as
accepted by the Government of India. National Coal Wage Agreements-V and VI (NCWA)
inter alia provided that in the coalfield areas, where the employees were
provided with residential quarters by Management and also electricity from the
bulk supply obtained from the Electricity Boards, they would be entitled to a
free consumption of 30 units (KWH) per residential quarter per month on a
uniform basis. It further provided that for any consumption beyond this, they
would be required to pay at the same rates at which the electricity supply
undertakings charged the coal companies.
Audit scrutiny revealed that the consumption of electricity
by the employees was in excess of the limit stipulated. However, no recovery of
charges for excessive consumption was made from the employees in contravention
of the terms and conditions of the NCWA. The amount of electricity consumed by
the employees between April 1999 to March 2002 in excess of the above limit
worked out to Rs.219.77 crore.
Although the case of non-recovery of excess electricity
charges amounting to Rs.3.37 crore from the employees of one area (Jamuna and
Kothma) of the Company was reported in the para 15.3.1 of the Report of the
Comptroller and Auditor General of India No. 3 (Commercial) of 2001, no action
had so far been taken to recover the excess charges from the employees of the
Company.
Management stated (June 2000) that electricity charges were
not being recovered from the employees due to non-installation of meters in
their residential quarters and that the matter had been taken up with Coal India
Limited for keeping this issue in view while finalising the ensuing NCWA-VI.
They also stated that the excess consumption of electricity also included the
consumption on general services.
Ministry endorsed (August 2002) the reply of Management,
which stated (February 2002) that as the issue involved was common to all the
subsidiaries of CIL, the matter was referred to CIL for necessary action.
The reply is not tenable since installation of meters was not
an insurmountable problem. In fact, non-installation of meters would encourage
employees to resort to indiscriminate use of electricity for their energy needs.
Even in the NCWA-VI finalised in December 2000, no corrective action had been
taken by CIL. Further, consumption of electricity on general services was very
nominal as compared to the total consumption in domestic area.
Thus, due to non-recovery of electricity charges from the
employees in contravention of the terms and conditions of the NCWA, the Company
suffered an avoidable loss of Rs.219.77 crore during the period April 1999 to
March 2002.
|