CHAPTER 20
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
National Highways Authority of India
20.1.1 Loss of revenue due to delay in collection of toll
Delay in collection of toll in the Gurgaon-Kotputli section of National
Highway No.8 had resulted in a loss of revenue of Rs.8.76 crore.
As per the policy of the Government of India the users of all
the recently improved national highways shall have to pay toll for its usage.
The toll is to be collected at the rates and periods determined by the
Government of India, which are to be notified in the official gazette. To
implement the above policy the National Highways Authority of India (Authority)
shall have to put in place the required infrastructure facilities for the toll
collection.
Four-laning work and strengthening of the 126 km. National
Highway section of National Highway No.8 between Gurgaon (Haryana) and Kotputli
(Rajasthan) was substantially completed during September 2000 and March 2001 in
two phases at a cost of Rs.385.50 crore. But as there was a delay in awarding of
work relating to setting up of permanent toll plaza, the Authority decided
(August 2001) to make arrangements for temporary toll plaza to collect toll from
1 October 2001. As temporary toll plaza was also not ready by 31 December 2001
toll could not be collected by the Authority despite issue of necessary gazette
notification by the Government of India permitting the Authority to collect toll
in the above stretch with effect from 1 January 2002. Ultimately the Authority
started collection of toll from 15 March 2002 when temporary toll plaza was set
up.
The delay on the part of Management in the construction
tolling booths resulted in the non levy of toll from the road users for a period
of 73 days resulting in a loss of revenue of Rs.8.76 crore (calculated
at the rate of Rs.12 lakh per day being the average toll collection from 15
March 2002 to 31 March 2002).
Management stated (June 2002) that there was no delay
inasmuch as after notification of the rates by the Government of India,
temporary toll plaza was constructed and the collection of toll commenced from
15 March 2002 onwards. Contention of Management is not tenable as Government of
India specified 1 January 2002 as the date to levy and collect toll whereas the
Authority started collection from 15 March 2002. The failure of the Authority
for timely action for the awarding of work relating to permanent toll plaza
immediately after substantial completion of four-laning work or expeditiously
construct temporary toll plaza, caused the delay in levy and collection of toll
to the extent of Rs.8.76 crore.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
20.1.2 Loss due to non-recovery of extra cost on reawarding of work
Failure of the Authority to recover extra cost from a
contractor on reawarding of work necessitated due to fault of the contractor
resulted in a loss of Rs.4.95 crore to the Authority.
The Authority awarded (July 1996) an item rate contract for
four laning work and strengthening of the 126 km National Highway between
Gurgaon (Haryana) and Kotputli (Rajasthan) to a contractor, a joint venture of
M/s. Birla GTM Entrerpose Limited (BGE) and M/s. Enterprise Jean Lafebvre (EJL),
at a cost of Rs.261.81 crore. The work was scheduled to be completed by March
2000. M/s. SMEC Limited, Australia (SMEC) was the supervisor engineer for the
construction work.
As the progress of work during the initial stages of its
execution was not satisfactory, a high level review meeting was convened at the
Authority’s Headquarters on 25 January 1997 between the Authority, SMEC and
partners of the contractor to express their serious concern on unsatisfactory
performance of the contractor. During this meeting EJL informed that there was
no joint venture for the contract with BGE. On noticing the misrepresentation of
the joint venture the Authority obtained the advice of the legal advisor as per
the recommendation of SMEC and Asian Development Bank (ADB). On the advice of
the legal advisor, as per the recommendation of SMEC and ADB, the Authority
rescinded the contract of BGE-EJL (joint venture) on 9 June 1997. As per
decision of the Board of Directors of the Authority (4 July1997) and approval of
ADB the above work was awarded to the next lowest bidder BSC-RBM-PATI (joint
venture) at a price of Rs.264.66 crore on 27 August 1997. In order to settle the
account of the first contractor SMEC, the engineer recommended to recover
Rs.5.17 crore towards interest on unutilised mobilisation advance, the Authority
administrative cost, ADB loan cost, escalation costs and consultants costs from
the defaulter contractor as per clause 2.6 of general conditions of the
contract.
Thereafter, balance work valuing Rs.259.71 crore was awarded
(July 1997) to the next lowest bidder at a cost of Rs.264.66 crore with the
scheduled date of completion as March 2001. The Authority did not recover the
increase in the direct cost of Rs.4.95 (Rs.264.66
crore minus (Rs.261.81 crore plus Rs.2.10 crore being the amount paid to the
first contractor for work done) crore which
resulted on awarding the work to the next contractor.
Thus, failure of the Authority to recover extra cost from a
contractor on reawarding of work resulted in a loss of Rs.4.95 crore.
Management stated (April 2000) that their engineer, SMEC did
not consider recovery of the price difference as a justified claim and at the
time of rescinding the contract, no mention of reaward of the work at the risk
and cost of the previous contractor and recovery of additional cost from them
was made to avoid litigation.
Contention of Management is not tenable as recommendation of
SMEC was defective since the legal advisor had clearly stated that the Authority
was within its rights to claim damages including any direct increase in the cost
of work. Depending upon the recommendation of a private party appointed as an
engineer and foregoing of a justified claim on the apprehension of a legal case
was not a prudent Management decision. It is also not understood as to how this
firm was selected as a contractor without verifying the terms and conditions of
joint venture ab initio.
Ministry, while endorsing the views of Management, stated
(September 2002) that the matter was being referred to Ministry of Law for their
opinion.
20.1.3 Irregular payment of royalty
Irregular payment of royalty to the contractor resulted in an
excess payment amounting to Rs.4.47 crore.
The Authority awarded (July 1997) a contract for four-laning
work and strengthening of the 126 km National Highway between Gurgaon (Haryana)
and Kotputli (Rajasthan) to a contractor, at a cost of Rs.264.66 crore which was
completed in March 2001 at a cost of Rs.385.50 crore.
As per the agreement any new taxes and duties levied by
Central/State Government/Local Authority, which would directly affect the cost
of the materials other than those already considered in price adjustment should
only be paid to the contractor. However, such additional cost shall not be
separately paid if the same has already been taken into account in the indexing
of any input to the Price Adjustments Formula.
Despite this clear stipulation the Authority paid Rs.4.47
crore as royalty to the contractor under clause 70.8 of the agreement after
making payment of Rs.4.52 crore towards increase in the cost of general
materials under clause 70.3 of the agreement. This resulted in an excess payment
of royalty amounting to Rs.4.47 crore to the Contractor.
Management stated (June 2002) that there was no excess
payment as the payment had been released under clause 70.8 of the agreement.
Contention of Management is not tenable as Clause 70.8
clearly specified that additional royalty should not be paid if it was covered
under Price Adjustment Formula.
Thus, the fact remains that Authority made excess payment of
Rs.4.47 crore to a contractor, which it was not entitled to.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
20.1.4 Avoidable payment of penal interest
Non remittance of tax deducted under the Income Tax Act
within the due date resulted in avoidable payment of penal interest
amounting to Rs.51.63 lakh. The Authority had been engaging the services of various
overseas consultants from different countries for the development and
maintenance of the National Highways and associated facilities. These foreign
consultants were paid remuneration in foreign as well as in Indian currency
according to the terms of the contracts entered into with them. As per the
provisions of Sections 195 and 195 A of the Income Tax Act, 1961, the Authority
was responsible for deducting income tax at the time of making payment towards
remuneration to the foreign consultants. As per Rule 30 (2) of the Income Tax
Rules, the tax deducted had to be paid to the Government within one week from
the last day of the month in which the deduction was made and any violation in
this regard would attract levy of penal interest as per section 201(1)(1 A) of
the Income Tax Act.
Scrutiny by Audit revealed that the Authority had neither
remitted the tax deducted from the remuneration paid to foreign consultants
amounting to Rs.3.76 crore for the period from 1997-98 to 1999-2000 nor filed
the quarterly return with the Income Tax authorities. As a result, the Authority
had to pay (May/June 2000) avoidable penal interest of Rs.51.63 lakh to the
Income Tax authorities while remitting the tax deducted by them.
Management stated (February 2002) that the delay was mainly
due to absence of correct interpretation of the tax provision, which was beyond
the control of the Authority. The reply is not tenable as ignorance of the
provision of the Income Tax Act cannot be an excuse for non-payment of tax.
Ministry stated (August 2002) that the Authority had been
directed to fix responsibility for non remmitance of the tax deducted from the
remuneration paid to foreign consultants which resulted in payment of penal
interest.
20.1.5 Irregular reimbursement of medical claims
Liberalisation of medical reimbursement rules for the
employees of the Authority in violation of Central Civil Services (Medical
Attendance) Rules, 1954 resulted in an irregular payment of Rs.45.66 lakh. The Authority in accordance with Section 35 (1) and 2 (b) of
the National Highways Authority of India Act, 1988, notified their Medical
Attendance and Treatment Regulations (Regulations), w.e.f. 11 September 1997. As
per clause 3 of the said regulations, an officer or employee would be entitled
to reimbursement of expenditure incurred on medical treatment of self and
members of family provided by a registered medical practitioner and/or approved
hospital, subject to a maximum of one month’s basic pay per year. The
Regulations did not specify the procedure for preferring/processing the medical
claims. Clause 10 of the said Regulations stipulated that matters in respect of
which no specific provisions had been made in the Regulations, would be
regulated under the provisions of the Central Civil Services (Medical
Attendance) Rules, 1954 (Rules) as amended from time to time, and the
instructions issued thereunder by the Central Government.
A review by Audit revealed that the Authority processed
requests for medical reimbursement claims along with necessary cash receipts in
support of the claims till January 2001. Thereafter, Management without the
approval of the Board or the Government, decided (January 2001) to reimburse
medical expenditure within the ceiling limit on the basis of self-certification
by the employee thereby dispensing with the production of supporting documents
as required under the Rules. The said internal order was made effective
retrospectively from April 2000, as a result of which, the Authority paid
Rs.45.66 lakh including arrears (from 1 April 2000 to 14 February 2001) of
Rs.1.68 lakh to the employees working in the Corporate headquarters of the
Authority and 24 Project Implementation Units from April 2000 to March 2002.
Management stated (April 2002) that the decision to reimburse
the expenditure towards out-patients/outdoor treatment up to the limit of one
month’s basic pay against actual expenditure incurred and certified by the
officer or the employee was taken to facilitate timely and quick disposal of the
reimbursement claims.
Contention of Management is not tenable, as the Rules framed
by the Central Government stipulating that the claims shall have to be preferred
along with the necessary supporting documents, cannot be violated on the plea of
simplification and quick disposal of the claims.
The matter was referred to Ministry in June 2002; their reply
was awaited (September 2002).
|