CHAPTER 18
MINISTRY OF POWER
Nathpa Jhakri Power Corporation Limited
18.1.1 Gross negligence before putting up DPR for formal approval
Due to negligence, mistake in the computation of the capacity
of reservoir could not be detected before starting the execution of the works.
As a result, the peaking availability of power during lean season would now be
1.5 hours against 3 hours as planned earlier. This would lead to a generation
loss of 713 million units per annum.
Nathpa Jhakri Hydroelectric Project (NJHP) was conceived to
generate 1500 MW of power daily during monsoon and to meet the peaking
requirement of 3 hours twice a day during lean season. Himachal Pradesh State
Electricity Board (HPSEB), the initial executing agency, had prepared detailed
project report (DPR) in 1986 based on the data supplied by the Survey of India (SOI)
in 1981-82. The DPR envisaged 60.5 metre high concrete gravity dam on Satluj
river at Nathpa and a pondage of 457 hectare metre (ham) based upon a reference
benchmark at Earth Level (EL) 1526.933 metre.
In May 1988, Nathpa Jhakri Power Corporation Limited
(Company) was formed for taking up the NJHP. In the meanwhile, the SOI had
revised the benchmark from EL 1526.933 metre to EL 1524.700 metre in 1987.
However, before seeking the formal approval of the Government of India (GOI),
the parameters of various components of NJHP were not scrutinised by the
Company/HPSEB for affirming the veracity of the data and the correctness of
calculations. Even the agencies of the GOI involved in approving the NJHP could
not detect the error. As a result, GOI approved (April 1989) the capital
investment of Rs.1678.02 crore for NJHP, based on the wrongly-assumed level of
the elevations of various structures of the dam complex.
Even before initiating the process for invitation of bids for
major works, the Company did not take care to verify the details and awarded the
works in May 1993 on the basis of the faulty DPR. The Company could find
discrepancies only in June 1994 during detailed survey at the time of
construction of the dam. The matter was taken up with the SOI, which confirmed
(December 1994) that the heights supplied previously were provisional.
The Company informed (June 1995) the Central Electricity
Authority (CEA) that the pondage capacity would be insufficient to meet the
peaking hour requirement. The CEA observed (September 1995) that there were also
mistakes in the computation of storage capacity of the reservoir. When the
Company carried out detailed analysis of the various factors, it noticed that
the capacity of reservoir had decreased from 457 ham to 165 ham due to an error
in the computation at the initial stage (3.74 metre), inaccuracy of the original
surveys (2.43 metre) and rockfalls/flash floods (0.43 metre). This, in effect,
reduced the peaking availability of power from the originally planned 3 hours to
1.5 hours.
As a result, the project would not be able to generate the
envisaged peaking power of 3 hours unless height of the dam was increased by 7
metres. The Government of Himachal Pradesh (GOHP) has not agreed to an increase
in the height of the dam on the plea that it would pose a serious danger to the
safety of its own power plant located nearby.
Management stated (June 2001) that the effective control of
NJHP by the Company had materialised only in February 1992 and the discrepancy
was noticed while carrying out departmental survey in June 1994, after the award
of the main civil works. They also stated (April 2002) that an expert committee
had been constituted in December 2001 to resolve the issue with the State
Government.
The reply is not convincing. HPSEB was in charge of the NJHP
until the formation of the Company in May 1988. Both the entities, however,
failed to detect the mistakes before submitting the DPR for the approval of the
GOI and later before commencing the execution of the work.
Thus, due to negligence, mistake in the computation of the
capacity of reservoir could not be detected before starting the execution of the
works. Had the Company/HPSEB as well as other agencies of the GOI examined the
DPR with due care before the formal approval of the GOI in April 1989, the
capital investment of Rs.1678.02 crore, which has now increased to Rs.7666.31
crore (at June 1998 prices), could have been scaled down suitably. Even if the
project is now executed without increasing the height, it may not give the
desired results of 3 hours of continuous peaking power and there would be annual
generation loss of 713 million units as estimated by Management. Audit could not
obtain any evidence of an inquiry into the gross negligence at the level of the
Company, nor could it obtain any evidence of revision in administrative
procedures to safeguard against repetition of such costly errors in the future.
The matter was referred to Ministry in April 2001; their
reply is awaited (September 2002).
National Hydroelectric Power Corporation Limited
18.2.1 Non-realisation of funds
Due to lapse in not taking due care at the time of
finalisation of the MOU for recovering the TDS from the contractor, the Company
has not realised funds amounting to Rs.7.41 crore for the last eight years.
National Hydroelectric Power Corporation Limited (Company)
entered (September 1989) into an agreement with a French consortium for
construction of Dulhasti hydroelectric project on turnkey basis. According to
the agreement, the Company was required to make advance payment to the
consortium and also bear the liability of income tax. Accordingly, a sum of
Rs.7.41 crore being the tax deducted at source (TDS) on advances of Rs.107.53
crore was deposited by the Company with the Income Tax Department (ITD) on
behalf of M/s. Dumez Sogea Borie (DSB), a member of the consortium.
As DSB suspended the work in May 1992 due to various reasons,
the Company signed a Memorandum of Understanding (MOU) with it in June 1994 with
the approval of the Government of India. The MOU was regularised by means of a
Recession Agreement signed in June 1995, whereby the advances of Rs.107.53 crore
were recovered/adjusted by the Company.
The Company, however, failed to include a clause in the
agreement for recovery of TDS on the recovered advances, even though this was
vetted by their legal advisor. Even thereafter, no action was taken by the
Company for almost two years. Only on 27 May 1996, the Company asked the
consultant of DSB to take appropriate steps for refund of tax. In March 1997,
DSB awarded the power of attorney in favour of a consultant (attorney) of the
Company for pursuing the matter with the ITD.
The attorney filed (April 1997) a petition before the
Commissioner of Income Tax (CIT) for refund of tax after the expiry of a period
of one year from the date of the assessment (December 1993) as stipulated under
section 264 of the Income Tax Act. The petition was, however, rejected (May1999)
by the ITD on the plea that DSB had already taken credit of this tax in France.
Management contended (March 2001) that the Central Board of
Direct Taxes had asked (October 2000) the CIT to intimate the French tax
authorities to reverse the credit taken by DSB in France and that the
application for refund might be admitted after expiry of the period of one year
under section 264(3) of the Income Tax Act. They also contended (May 2002) that
after filing the fresh application under section 264 (3), the matter was
discussed with ITD and it was presumed that the fresh application had been
accepted. Ministry has endorsed (July 2001) the reply of Management.
However, the fact remains that the refund has not been
granted so far (May 2002). Further, Management cannot be absolved of its
responsibility for taking due care at the time of finalisation of the MOU with a
foreign contractor.
Thus, the Company has not realised funds amounting to Rs.7.41
crore for the last eight years due to its failure in ignoring the aspect of
recovery of TDS at the time of finalisation of the MOU.
18.2.2 Extra payment of customs duty to a contractor
The Company did not restrict the payment of customs duty in
proportion to the actual cost of the imported equipment. This resulted in an
extra payment of Rs.2.87 crore to the contractor, which led to an undue benefit
to a private party.
The Company awarded (June 1999) the work of Chamera
Hydroelectric Project (Stage-II) to Indo-Canadian Hydro Consortium on turnkey
basis. The civil works were being executed by M/s. Jaiprakash Industries Limited
(contractor), a member of the consortium.
According to the contract agreement, the contractor was to
arrange all the construction plant and equipment and the cost thereof was to be
borne by the Company. The total payment on this account was to be limited to
Rs.57 crore for indigenous equipment, US$ 12.70 million for imported equipment
and Rs.20.14 crore towards customs duty, port landing, inland transport and
insurance on the imported equipment. Any increase/decrease in the customs duty
due to variation in the customs tariff and exchange rate was also to be borne by
the Company.
The contractor imported (November 1999 to June 2001)
equipment valuing US$ 10.16 million and proposed to import some equipment
valuing US$ 0.73 million subsequently. Accordingly, against the ceiling
of US$ 12.70 million, the contractor would utilise only US$ 10.89 million for
imported equipment. For the remaining amount of US$ 1.81 million (US$ 12.70
million minus US$ 10.89 million), the Company allowed (May 2002) the contractor
to procure indigenous equipment by converting the prices at the prevalent rate
of exchange.
Though the Company allowed the contractor to import equipment
for lesser amount, it did not restrict the payment of customs duty in proportion
to the actual cost of the imported equipment. Proportionate amount of the
customs duty, based on the cost of the imported equipment valuing US$ 10.89
million, worked out to Rs.17.27 crore only. However, the Company paid the total
amount of Rs.20.14 crore towards customs duty, etc., besides the variation of
Rs.1.33 crore, against the contractor’s claim of Rs.25.93 crore.
The contractor claimed (May 2001) higher amount of Rs.25.93
crore on the plea that the customs duty indicated in the bid was based on the
concessional rates under project imports, whereas the customs department had
levied duty at the full rates. The Company rejected (July 2001) the claim on the
ground that the contractor had never approached it for a Project Authority
Certificate prior to a favorable award of Customs Tribunal in some other case.
However, the Company restricted the payment of customs duty to Rs.20.14 crore
and not to Rs.17.27 crore based on the corresponding amount of imported
equipment.
This resulted in an extra payment of Rs.2.87 crore (Rs.20.14
crore minus Rs.17.27 crore) to the contractor, which led to an undue benefit to
a private party.
Management stated (June 2002) that the Company was liable to
pay customs duty limited to Rs.20.14 crore plus variation in respect of the
imported equipment. Accordingly, the amount on this account was restricted to
Rs.21.47 crore including the variation of Rs.1.33 crore against the actual
expenditure of Rs.25.93 crore of the contractor.
The reply is not tenable as customs duty of Rs. 20.14 crore
was payable on the total imported equipment valuing US$ 12.70 million and
notwithstanding the actual expenditure incurred by the contractor, the payment
of the customs duty should have been restricted to Rs. 17.27 crore based on the
cost of equipment imported.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
Power Grid Corporation of India Limited
18.3.1 Mismatch between the transmission system and generation project
Due to its failure in monitoring the progress of the
generation project, the Company constructed the transmission system, 45 months
in advance of its requirement. As a result, the Company had to bear loss of Rs.
26.44 crore on account of the interest, operation and maintenance expenditure
till March 2002. Besides, the Company was also not able to earn annual revenue
of Rs. 36.74 crore since April 2000.
The works relating to Dulhasti Hydroelectric Project (DHEP)
were awarded by National Hydroelectric Power Corporation Limited (NHPC) to a
French Consortium (FC) in September 1989, with the schedule commissioning by
July 1994. Originally, the transmission system associated with DHEP was also to
be constructed by NHPC. After formation of Power Grid Corporation of India
Limited (Company), the construction of the transmission system was assigned to
it in 1992. In view of the urgency involved, the Company evolved (January 1992)
a contingency scheme for construction of transmission line between
Dulhasti-Kishenpur at an estimated cost of Rs.137.69 crore so as to match
commissioning of the transmission system with the generation project.
In the meanwhile, the FC suspended the work of DHEP in May
1992 due to geological fault encountered in the tunnel and finally abandoned the
related contractual obligations in August 1992. The FC also took up the issue of
stoppage of works with Ministry of Power in September 1992. Despite these
developments clearly indicating the slippage in the construction schedule of the
DHEP, Ministry gave a go-ahead for the contingency plan in December 1992.
The Company failed to ascertain the tardy progress of the
generation project and awarded the works relating to associated transmission
line in January 1993. In the process, the Company started the execution of the
transmission line, whereas the related generation project was lying abandoned.
The Company came to know only in September 1994, when NHPC
confirmed that the commissioning of DHEP would be delayed by 5-6 years from the
date of re-start of work. The remaining work of DHEP was re-awarded by NHPC only
in March 1997. In view of the inordinate delay in commissioning of the
generation project, the Company decided (January 1995) to upgrade the 220 KV
contingency scheme to 400 KV transmission line. The upgraded transmission line
was commissioned in March 2000 at a cost of Rs 195.59 crore far in advance of
the generation project, which is expected to be commissioned by December 2003
only. As such, the mismatch between the construction of transmission line and
generation system due to lack of monitoring of the progress of the generation
project on the part of the Company as well as Ministry has resulted in idling of
the transmission line since March 2000.
Management stated (May 2002) that:
- The Company had been keeping itself abreast of the
progress of the generation project. When the work was bogged down due to
militancy and NHPC confirmed in September 1994 that the DHEP would be
delayed by at least 5 to 6 years, the status of the transmission system was
reviewed. However, by that time most of the foundations were cast.
Accordingly, the decision was taken to dispense with the contingency scheme
by reviving the original system of up-gradation to 400 KV line. Once the
execution of transmission project was commenced, it was not possible to
fluctuate its scheduled date of completion, even if the generation project
was delayed.
- The Company declared the transmission line commissioned
in March 2000 in accordance with the tariff notification of the Government
of India (December 1997) and was entitled to tariff from the date of its
commercial declaration.
The reply of Management is not tenable due to the following:
- The work on generation project had already been stalled
in August 1992 before award of the work of transmission line in January
1993. Accordingly, the Company should have deferred the process of award of
works till the resolution of the problems in the construction of the
generation project, especially in light of the fact that the gestation
period of the hydroelectric projects is more than that of the transmission
system. As such, had the Company monitored the progress of the DHEP, it
would not have gone ahead with the award of the works relating to
transmission system ab initio. In fact, the Standing Committee of the
Planning Commission, while reviewing the time and cost overrun, had also
commented (September 2001) on the poor monitoring on the part of the
Company.
- State Electricity Boards were reluctant to pay
transmission tariff, as there was no gain to them in such transmission
projects. Further, bulk purchase tariff agreements for this project were yet
to be finalised with the SEBs. Accordingly, the Company had to bear the
interest cost without being able to recover any revenue from the
transmission system till the commissioning of the generation project.
Thus, due to its failure to monitor the progress of the
generation project, the Company constructed the transmission system, 45 months
in advance of its requirement. As a result, the Company had to bear loss of Rs.
22.70 crore on account of interest on borrowed funds, besides expenditure of Rs
3.74 crore towards operation and maintenance of the system from the date of its
commissioning till March 2002. Moreover, the Company was also not able to earn
annual revenue of Rs. 36.74 crore since April 2000.
The matter was referred to Ministry in June 2002; their reply
was awaited (September 2002).
18.3.2 Avoidable extra expenditure on import of insulators
Failure of the Company in not considering the available lower rates before
placing the order resulted in procurement of insulators at extra cost of Rs.
28.69 crore.
The Company invited (June 1994) global tenders for
procurement of line material including 4,34,050 number of 210 Kilo Newton (KN)
disc insulators (insulators) for (800 KV) Kishenpur-Moga transmission system (KMTS),
against which only two bids were received from foreign firms. Since both the
firms expressed their inability to supply such a large order within 24 months,
the Company split (10 January 1995) the order between them at an average landed
cost of Rs.1643 per insulator.
In the meanwhile, the Company had opened (13 December 1994)
another bid for procurement of 210 KN disc insulators for (400 KV) Nathpa Jhakri
transmission system (NJTS). The lowest evaluated rate of Rs.982 per insulator
received for NJTS was much lower than those received for KMTS. However, the
Company did not take cognizance of the lower rate to explore the possibility of
reduction in rates before placing the letters of award for KMTS in January 1995.
Thus, by not reviewing its decision for procurement of the
insulators for KMTS at exorbitant prices, the Company had foregone an
opportunity to save extra expenditure to the extent of Rs. 28.69 crore.
Further, while rejecting the bid of Bharat Heavy Electricals
Limited (BHEL) for NJTS on the ground that it did not have the requisite
experience, the Company decided (January 1995) to place a developmental order on
BHEL for supply of 1,13,800 nos. of insulators at Rs.965 per insulator for 400
KV and 800 KV lines associated with Tehri Hydroelectric Project (THEP). Clearly,
therefore, a developmental order could have been placed on BHEL for KMTS also,
where the awarded rate was higher by Rs.678 per insulator. However, the Company
did not do this.
Management contended (May 2002) that specification of
insulators for use in 800 KV lines and 400 KV lines was different and therefore,
comparison of prices received from a qualified bidder with those quoted by a
non-qualified bidder for different voltage line and having different
specification could not be made. They further stated that a contract under
vendor development was awarded on BHEL in order to develop them as an indigenous
source of 210 KN insulators.
The reply is not tenable because notwithstanding the
difference in technical specification, both the foreign firms had quoted almost
the same rates for 800 KV line (KMTS) and 400 KV line (NJTS). Further, based on
the experience and expertise of BHEL as acknowledged by the Company during the
evaluation of bids for NJTS, the developmental order was placed on BHEL at the
same rate for 400 KV as well as 800 KV lines of THEP. This establishes that
difference in technical parameters did not have any impact on the price of 210
KN insulators.
Thus, failure of the Company in not taking into account the
available lower rates before placing the order resulted in procurement of
insulators for KMTS at exorbitant price. In fact, Ministry of Power had also
commented upon (August 2001) the high cost of these insulators.
The matter was referred to Ministry in June 2002; their reply
was awaited (September 2002).
18.3.3 Avoidable burden of commitment charges and
interest on foreign exchange loan
Delay in cancellation of the unutilised foreign exchange loan
coupled with premature withdrawal of loan resulted in avoidable burden of
Rs.5.98 crore on account of finance charges.
The Company entered into an agreement (March 1993) with the
International Bank for Reconstruction and Development (World Bank) for loan of
US$ 350 million to finance its various transmission projects specified under
‘Powergrid System Development Project-I’ (PSDP-I). According to the agreement,
the Company was required to avail the entire amount of loan before June 2000,
and could also cancel, at any time before the closing date, all or part of the
unutilised amount of loan. The agreement also stipulated payment of commitment
charges at the rate of 0.25 per cent per annum on the uncancelled and
undisbursed balance of credit.
Audit scrutiny of the records revealed that the Company did
not assess the requirement of the funds before commencing the drawl of the loan
to avoid payment of interest on the unutilised funds. Nor did it review the
utilisation of the disbursed funds so as to ascertain the expected amount of
surplus loan to be cancelled to avoid huge payment of commitment charges. As a
result, the Company incurred an avoidable expenditure of interest and commitment
charges aggregating Rs.5.98 crore as discussed below:
(i) The Company withdrew an amount of US$ 25 million on 31
March 1993 without assessing the requirement of funds and kept the same in a
deposit account of State Bank of India, New York. It started utilising the funds
only from 18 August 1993 and could utilise only a meagre amount of US$ 2.48
million till 24 October 1994, leaving a huge minimum balance of US$ 22.52
million in the bank for more than 18 months.
Due to drawal of the funds far in advance, the Company
incurred an avoidable expenditure of interest amounting to US$ 1.339 million
(equivalent to Rs.4.22 crore) being the excess of the amount of interest paid to
the World Bank over that earned on the deposit account.
Management stated (June 2002) that it was the first direct
loan from the World Bank. The reply is not convincing and only shows ineffective
cash planning on the part of the Company.
(ii) The Company awarded most of the contracts relating to
the PSDP-I by September 1995 and reviewed the utilisation of the funds in
December 1996. It estimated a saving of US$ 50 million and decided to utilise
the same for a new project. Thereafter, the Company did not review the position
for more than two years, even though the remaining contracts were awarded by
February 1998 and the financial commitments became known to the Company.
The Company carried out the next review only in March 1999
and assessed that a sum of US$ 111.43 million would be surplus, due to lower
prices quoted by the bidders and the appreciation in the value of US Dollar
vis-à-vis Indian Rupees. Accordingly, after retaining an amount of US$ 36.43
million to meet capital expenditure on some new projects, the Company requested
(March 1999) the World Bank to cancel the remaining amount of US$ 75 million
which was accepted by the latter in April 1999.
The World Bank also extended (June 2000) the time limit for
utilisation of the remaining portion of the loan till December 2000. As the
Company could not utilise the same even during the extended period, the World
Bank cancelled (July 2001) the unutilised amount of loan by closing the loan
agreement.
Had the Company monitored the utilisation of funds regularly,
it would have saved commitment charges amounting to Rs.1.76 crore by
surrendering at least US$ 100 million in March 1998.
Management stated (June 2002) that it was felt prudent not to
surrender any part of the loan so as to obviate any financial constraints that
might be faced due to delay in finalisation of PSDP-II loan. Due to prolonged
sanction and delay in effectiveness of PSDP-II, the position was reviewed in
March 1999. They further stated that US$ 36.43 million could not be utlilised as
out of the proposed five projects, only two projects involving outlay of merely
US$ 5.75 million could materialise by July 1999.
The reply is not convincing as there was nothing on record to
indicate that the Company had reviewed the utilisation of the loan after
December 1996 till March 1999. Further, the World Bank had advised the Company
in July 1998 that projects specified in PSDP-II under their financial assistance
be continued and assured that the expenditure would be reimbursed under
retroactive financing option.
Thus, premature withdrawal of loan and the delay on the part
of Company in surrendering the surplus amount of the sanctioned loan resulted in
an avoidable burden of Rs. 5.98 crore on account of interest and commitment
charges.
The matter was referred to Ministry in June 2002; their reply
was awaited (September 2002).
18.3.4 Avoidable extra expenditure
Due to its failure to undertake negotiations with the lowest bidder, the
Company incurred an avoidable extra expenditure of Rs 51.77 lakh.
The Company invited (October 1997) bids for transmission line
packages for the transmission system associated with Sasaram Project which
included supply of 3525 kms of Aluminum Conductor Steel Reinforced (ACSR) moose
conductor. As the quantity of conductors was increased to 4710 kms of ACSR moose
conductor with additional requirement of 85 kms of ‘AACSR’ (Aluminum Alloy
Conductor Steel Reinforced) conductor owing to major changes in the
configuration of the transmission system, the Company decided (September 1998)
to split the procurement of conductors in two packages i.e. C1 (ACSR-2295 kms)
and C2 (ACSR- 2415 kms and AACSR- 85 kms) by issuing corrigendum to the
‘invitation for bids’.
The Company received (October/November 1998) nine bids for C1
package and six bids for C2 package. The offers of M/s. Sterlite Industries
(India) Limited (Sterlite) relating to ACSR conductors at ex-works prices of US$
2976 per km for C1 package and US$ 3026 per km for C2 package, were found to be
the lowest and technically responsive individually in both the packages. In
fact, the same bidder had quoted, at the same time, different rates with a
variation of US$ 50 per Km for similar type of conductors under packages C1 and
C2. As both the bids were evaluated simultaneously, the price difference should
have caught their attention. It should have been a normal business behaviour of
the Company to seek the reasons for such a variation in price (unit rates) of
similar types of conductors and seek negotiations with the bidder to answer
these variations and bring down the quoted price of package C2 to that of
package C1.
However, the Company did not even take cognizance of
variation in unit rates and placed (March 1999) supply orders on Sterlite,
without negotiating the rates. Thus, the Company had to forego a clear, logical
case to save an extra expenditure of Rs.51.77 lakh. (1 US$ = Rs.42.87 as of 4
December 1998).
Management stated (November 2001) that the bids were invited
under two separate packages and there was no such condition in the bidding
documents that a bidder should necessarily quote same unit rate for both the
packages. They also contended that as per the World Bank’s procurement
guidelines, negotiation with the lowest tenderer should be resorted to only in
case the quoted prices were substantially higher than the pre-bid cost estimates
and in this case the awarded prices were lower by 25.22 per cent and 23.90 per
cent than the estimated cost.
Endorsing the reply of Management, Ministry added (April
2002) that the Company has recently adopted its new ‘Procurement Policy’ which
allowed negotiation with the bidder who happened to be the lowest in different
tenders with different rates for similar equipment, only in case the recommended
award price was higher than the estimated cost by 10 per cent and thus, there
was no lapse on the part of the Company by not undertaking negotiations with the
bidder.
The reply of Management/Ministry is not tenable, as the
Company evaluated the bids for C1 and C2 packages simultaneously and as such,
could compare the rates quoted by the same bidder in two packages. Further, the
guidelines of the World Bank did not specifically prevent the buyer from
undertaking negotiations with the lowest bidder and the new ‘Procurement Policy’
of the Company was not relevant in this case as the same was approved by the
Board of Directors in September 2001 after the award of packages in March 1999.
Thus, by not resorting to negotiation before placing two
different orders on the same supplier at the same time for the same items at
different rates, the Company incurred an avoidable extra expenditure of Rs.51.77
lakh.
Tehri Hydro Development Corporation Limited
18.4.1 Blockade of funds due to non-adjustment of advance
Non-adjustment of advance paid to M/s. Technopromexport
against the liability transferred to Power Grid Corporation of India Limited
resulted in blocking of Rs.2.78 crore since August 1993.
Prior to the formation of Tehri Hydro Development Corporation
Limited (Company), Uttar Pradesh Irrigation Department paid an advance of Rs.10
crore in 1988 under Indo Soviet Inter Government Agreement, to M/s.
Technopromexport (TPE), a Russian company for various works to be got executed
from them. However, after disintegration of Soviet Union, contracts with TPE
were not signed for execution of these works. One of these works was engineering
investigation of the Associated Transmission System (ATS).
The Company signed (October 1993) a Memorandum of
Understanding (MoU) with Power Grid Corporation of India Limited (PGCIL) and
transferred the works relating to the transmission lines and associated
sub-stations to PGCIL with effect from 1 August 1993 at a purchase consideration
of Rs.8.41 crore i.e. the book value of surplus of assets over liabilities.
These liabilities included Rs.2.78 crore payable to TPE towards ATS. In July
1995, the Company noticed that the advance paid to TPE remained to be adjusted
against the liability of Rs.2.78 crore transferred to PGCIL and took up the
matter with PGCIL for refund of the same. PGCIL requested (November 1999) the
Company to provide the investigation/survey report furnished by TPE for further
necessary action. Inspite of follow up by the Company, the matter has not been
resolved so far (July 2002).
Management stated (July 2002) that assets and liabilities
relating to ATS had been transferred to PGCIL through audited accounts as on 31
July 1993 and it had been regularly following up matter with PGCIL for recovery
of the amount.
Thus, non-adjustment of advance paid to TPE against the
liability transferred to PGCIL resulted in blocking of Rs.2.78 crore since
August 1993.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
|