CHAPTER 10
DEPARTMENT OF FERTILIZERS
Madras Fertilizers Limited
10.1.1 Award of contract to an ineligible party
The Company had to pay demurrage of Rs.78.23 lakh due to
appointment of an ineligible bidder as clearing and forwarding agent for
handling bulk cargo. Madras Fertilizers Limited (Company) took on loan about 20000
MT of imported urea from Department of Fertilizers (DOF) to supplement captive
consumption. The cargo was received (July 1999) at Chennai Port initially by
Indian Potash Limited (IPL) on behalf of the DOF. The Company in turn received
the cargo on ex-wharf basis from IPL as instructed by DOF. The Company entrusted
the work of receiving the bulk Urea on ex-wharf basis and subsequent
transportation to its clearing and forwarding (C&F) agent, M/s. Seashore
Logistics Private Limited, Chennai (SSL).
It was seen that the profile of bidders prepared by the
Company before selection of C&F agent distinctly mentioned that SSL had no
previous experience in handling bulk cargo at Chennai Port and no proof of
experience was provided for handling bulk cargo anywhere. On arrival of the ship
SSL failed to mobilise in time (a) adequate number of trucks (b) adequate labour
and (c) adequate funds to handle the shipment. This in turn caused abnormal
delay in discharging the cargo from the vessel. In order to hasten discharge of
the product, the Company allowed SSL to temporarily dump approximately 3000 MT
of the cargo in a transit shed inside the port area. As the cargo remained for
nearly three months in the transit shed, IPL as the ‘receiver’ of the cargo was
levied a demurrage of Rs.78.23 lakh. The Company subsequently paid demurrage
charges to IPL, as the material was taken on loan from DOF on ex-wharf basis.
The Company terminated the C&F contract (October 1999) to avoid further loss.
Thereafter, the Company incurred further handling and storage charges of Rs.9.45
lakh on the stocks left over by SSL at the termination of the contract for which
another C&F agent was engaged.
The following irregularities were committed by the Company to
favour SSL at the time of awarding the contract:
- The Chairman and Managing Director of the Company
approved (February 1998) limited tender enquiries to be sent to 12 firms
already registered with the company. SSL was not one among the twelve.
Subsequently, a separate tender enquiry was sent to SSL who was referred by
DOF.
- As per tender conditions, the bidder should have
possessed C&F agent licence to handle the bulk fertilizer cargo at the Port
of Chennai. But the Stevedoring Licence and the Customs House Agent Licence
produced by SSL at the time of bidding was not in their name but in names of
other parties, thereby disqualifying them from being considered. Still the
condition was relaxed by MFL and the contract was awarded to SSL. So far as
the condition relating to past experience was concerned, while the bid
submitted by one M/s. Continental Transport Agencies was rejected because it
was not meeting the tender norms pertaining to experience, the offer of SSL
was found acceptable by the Company and contract was awarded to it despite
inexperience in handling bulk cargo, this established the undue favour to
SSL in preference to bidders with past experience.
The Company admitted (July 2002) that SSL was awarded the
contract, which did not even possess Customs House Licence. The Company,
however, contended that it was in need of a new agent to encourage competition.
Ministry stated (October 2002) that there was no documentary evidence to show
that SSL was referred to by it.
The argument on the need to experiment with a new C&F agent
is not tenable because even a new agent should have fulfilied the norms for
selection specified by the Company, which in this case were ignored. Moreover,
floating limited tender enquiry to the empanelled C&F agent instead of open
tender cannot be stated to be an action to increase competition. Though, the
Company’s records expressely stated that SSL was referred to by DOF but it did
not elaborate upon the mode of communication. Ministry while stressing on the
absence of documentary evidence did not effectively counter the Audit
observation.
Thus, appointment of an ineligible party as C&F agent by the
Company clearly indicate the favour bestowed on the party, which resulted in an
avoidable loss of Rs.78.23 lakh. The case has a vigilance angle also in view of
the extraordinary way in which the SSL was selected.
National Fertilizers Limited
10.2.1 Avoidable expenditure in purchase of bags
The Company’s failure to follow the system of counter offer
to match the lowest price resulted in extra expenditure of Rs.2.82 crore on
purchase of 981 lakh bags during August 1999 to October 2000.
In July 1999, National Fertilizers limited (Company) assessed
its requirement of 417 lakh HDPE (High density poly ethylene)/Jute bags for 6
months for packing fertilizers produced by its 5 plants, involving an
expenditure of about Rs.38.50 crore. Since the packing material is a vital input
required for making uninterrupted despatches, the Company decided to place
orders (between August 1999 and October 2000) on multiple suppliers since the
lowest tenderer (L1) was not in a position to meet its entire requirement.
In line with CVC (Central Vigilance Commission) guidelines
(November 1998) which forbid negotiations with the parties other than lowest tenderer, the Company had a policy of distributing the supply orders amongst the
tenderers according to the ranking made in comparative statement at different
rates quoted by them without any price negotiations. However, CVC subsequently
clarified (March 1999) that in cases when the quantity to be ordered was much
more than what the L1 alone could supply, the quantity order might be
distributed in such manner that the purchase was done in a fair, transparent and
equitable manner.
It was noted that the Company continued the old practice of
placing orders at differential rates quoted by the firms even after issue of the
CVC clarification. This was also not commercially prudent as it resulted in
placement of orders for the same items at the same time at different rates. Even
when two members of the Tender Committee recommended (February 2000) that all
the suppliers be asked to match their rates with that of the lowest bidder, the
Company failed to negotiate prices with other tenderers and purchased 981 lakh
bags on three occasions at the weighted average price of Rs.9.03, Rs.9.89 and
Rs.10.72 as against the lowest price of Rs.8.88, Rs.8.68 and Rs.10.48 per bag
between August 1999 and October 2000.
Eventually in October 2000, the Board of Directors asked the
Tender Committee to make a counter offer to all the suppliers to match the
lowest price. Six bidders agreed to supply the bags at the lowest rate and the
quoted weighted average price of Rs.8.93 per bag came down to Rs.8.74 per bag in
January 2001 and further to Rs.8.45 in September 2001. The Company’s failure to
follow the system of counter offer to match the lowest price earlier resulted in
extra expenditure of Rs.2.82 crore on purchase of 981 lakh bags during August
1999 to October 2000.
Management stated (July 2002) that irrespective of the fact
whether the prices were negotiated or not, the price reasonability, keeping in
view the specification, was always ensured.
The reply of Management is not tenable as payment of rates
higher than the lowest rates to different suppliers for the same item was not
commercially prudent and resulted in extra expenditure. Besides after the
clarification of CVC in particular, the action of the Company was not at all
justified. The change in the policy subsequently resulted in the savings of
Rs.70.75 lakh in the purchase of 366 lakh bags in respect of tender finalised in
January 2001.
The matter was referred to Ministry in July 2002; their reply
was awaited (September 2002).
10.2.2 Blockade of funds in idle assets and consequent interest loss
Injudicious purchase of a premise at Bhopal without assessing
its requirement resulted in blocking of Rs.93.31 lakh and loss of interest of
Rs.1.20 crore.
The Board of Directors authorised (January 1991) Managing
Director of the Company to explore the possibility of buying a suitable office
premises at Bhopal from State Government Authorities. The Company firmed up
(January 1991) with Madhya Pradesh Housing Board (MPHB) for acquisition of two
separate premises comprising 9909 square feet (Paryawas Bhawan) and 9707 square
feet (Gautam Nagar) at Bhopal. While according approval to the acquisition of
the premises, the Board of Directors considered (February 1992) that premises at
Gautam Nagar would be used for Marketing Division and after taking over Paryawas
Bhawan, the Marketing Division would be shifted to the Paryawas Bhawan and
premises at Gautam Nagar would either be used for forthcoming Vijaypur Expansion
Project or it could be disposed of. This indicated that there was no firm
requirement for the two premises.
The possession of Gautam Nagar accommodation taken in June
1991 at a cost of Rs.50.85 lakh was being used for Marketing Division. However,
due to litigation between the MPHB and its sub contractor, the possession of
Paryawas Bhawan was delayed and actually taken in December 1999 at a cost of
Rs.93.31 lakh (Rs.78.47 lakh as cost of premises, Rs.7.15 lakh towards
registration charges & stamp duties and Rs.7.69 lakh towards incidential
expenditure till March 2002). The purchase cost of Paryawas Bhawan was partly
met by availing cash credit of Rs.75.27 lakh (Initial payment of Rs.7.50 lakh
was made in January 1991 and Rs.75.27 lakh was paid progessively up to March
1993)on
which an interest of Rs.1.20 crore had been incurred by the Company until
December 2001.
Since, the premises at Paryawas Bhawan was acquired without
visualising its utility, the property was found surplus even before the Company
took possession. Further, the expectations of Management for likely requirement
of the space for Vijaypur Expansion did not prove correct, hence, the
requirement of the property became redundant. Efforts of the Company in
exploring possibility of either to dispose of or rent out the premises through
press advertisements had not yielded any results so far (July 2002).
Management in its reply stated (March/August 2002) that
purchase of accommodation at Paryawas Bhawan was needed at that time (January
1991) but in view of changed circumstances the building could not be utilised
for Vijaypur Expansion Project.
Ministry also endorsed (August 2002) the views of Management.
The reply of Management/Ministry is not tenable as it hides the fact that ab
initio the requirement of two premises of such area was not correctly
analysed by the Company before conclusion of the deal. Even at that time the
Company reckoned that the premises might be required to be disposed of, if
considered necessary. As such, the marketability of the premises should have
been assessed prior to purchase. It was a case of bad planning.
Rashtriya Chemicals and Fertilizers Limited
10.3.1 Wasteful investment of Rs.44.91 crore on Formic Acid Plant
The Company’s investment of Rs.44.91 crore on Formic Acid
Plant was rendered wasteful due to poor implementation of project, lack of
market demand and high cost of production.
Formic Acid is used in leather, rubber, chemical and textile
industries. Rashtriya Chemicals and Fertilizers Limited (Company) decided in May
1995 to set up a 10000 Metric Tonnes per annum (MTPA) Formic Acid Plant at an
estimated cost of Rs.32.32 crore, as:
- the Company was manufacturing Methanol and Carbon
Monoxide, major raw materials required for production of Formic Acid;
- a market survey in 1994 had assessed the demand supply
gap in the country for the product to go up to 8000 MTPA by 1998-99; and
- a detailed feasibility report (DFR) prepared in February
1995 had envisaged break-even at 55.81 per cent capacity utilisation and a
payback period of 6.05 years on an assumed sales realisation of Rs.23000 per
MT and average cost of production of Rs.17255 per MT.
A firm quotation was obtained through global tender from Acid
Amine Technologists (AAT), USA, who had put up similar plants elsewhere, for
licence, process know- how and basic engineering. Agreement for basic design,
technical assistance and supervision of erection, start-up and commissioning was
entered into with AAT for US$ 0.85 million (Rs.3.76 crore) in July 1995 with a
time frame of 24 months for commissioning of the Plant.
The Plant was commissioned in September 1998 at a total cost
of Rs.44.91 crore. Commercial production started in December 1998, but the Plant
could run only intermittently due to repeated breakdowns. Although these were
subsequently resolved, the Plant could not run on full load due to certain
process problems such as low conversion of Methyl Formate to Formic Acid, high
catalyst consumption. AAT did not also demonstrate the guarantee test run as per
agreement and Company recovered Rs.33 lakh in December 1999 invoking bank
guarantee given by them. A test check of records revealed that at the time of
preparation of DFR, the Company did not possess sufficient data regarding prices
for open architecture system, since the Company was procuring this for the first
time.
The Company could produce only 1392 MT of Formic Acid between
December 1998 and June 2000. It suspended production thereafter because of (i)
high cost of production; (ii) lack of demand for the product as growth projected
in the market study did not materialise; (iii) excess production capacity in the
country due to setting up of new plants/ enhancement of capacity by competitors;
and (iv) unremunerative market price. A committee, which reviewed the viability
of the Plant, recommended (November 2000) discontinuation of production as it
was economically unviable.
Management stated (June 2002) that:
- While deliberating the viability of setting up this
Plant, the market survey report on demand supply, availability of
technology, capability of the technology suppliers, etc. were considered and
the decision to set up the Plant was justified at that time.
- The Plant could not be operated currently due to:
- acute shortage of gas, the basic input and consequent
increase in cost of steam on use of alternate fuel viz. Naphtha;
- lack of demand because of the main users viz. rubber
industry itself being in crisis, general slowdown of economic activities and
import liberalisation;
- cheaper imports because of steep reduction in custom duty
during last four to five years; and
- inability of the technology supplier to prove the
guarantees inspite of their earlier good track record.
While endorsing the views of Management, Ministry stated
(August 2002) that the plant was not in operation due to restricted availability
of basic input i.e. natural gas, high cost of production and low selling prices
which do not cover even the variable cost.
The reply of Management/Ministry is not tenable as:
- the demand supply gap in 1994-95 was only 1470 MT and the
projected gap by 1998-99 as per the market survey, which in itself was over
optimistic, was only 8100 MT. This did not justify setting up a 10000 MT
Plant;
- probability of competition from new entrants was also not
considered in the market survey;
- adverse impact of liberalisation of economy and custom
duty reduction were known factors in 1995 when the project was taken up;
- allocation of gas for use in boilers for generation of
steam was only a fallback option as shortage of gas had been known to the
Company from 1992-93 onwards, that is, well before commencement of the
project; and
- although the technology supplier, AAT, had acquired the
patent and licence for setting up Formic Acid Plants in 1986, they had no
proven track record at the time of their selection by the Company in 1995.
Thus, setting up a Formic Acid Plant based on unrealistic
assessment of market demand and poor implementation of the project, leading to
process defects and high cost of production rendered operation of the Plant
economically unviable and the investment of Rs.44.91 crore thereon was rendered
wasteful.
|